8 Ill. Adm. Code 900.303
Procedures
Section 900
Section 900.303 Procedures
a) The notice of intent to construct shall contain the following
items:
1) A legal description of the land on which the livestock
facility will be constructed;
2) The names and addresses of the owners or operators of the
facility;
3) The type and size of the facility;
4) The existing, proposed, and total number of animal units at
the facility;
5) The names and addresses of the owners, including local, State,
and federal governments, of the property located within the setback areas;
6) The distance to the nearest residence, non-farm business, and
common place of assembly as referenced in the definition of "populated
area" in Section 900.103 of this Part;
7) A map or sketch showing the proposed facility and setback
areas, identifying within the applicable setback areas all the residences,
non-farm businesses, and common places of assembly as referenced in the
definition of "populated area" in Section 900.103 of this Part; and
8) A statement identifying whether a request for decrease in
setbacks, pursuant to Section 900.202(f) or (g), has been sought and whether
the request has been granted or denied yet.
b) For livestock management or livestock waste handling
facilities that are not subject to the public informational meeting process as
outlined in Section 12 of the Livestock Management Facilities Act [510 ILCS 77]
and Subpart D of this Part, the following procedures shall be followed:
1)
Upon receipt of the notice of intent to construct form, the
Department shall review the documents to determine if all information has been
submitted or if clarification is needed. The Department shall, within 15
calendar days
after
receipt of a notice of intent to construct form,
notify the owner or operator that construction may begin,
only after
receipt and approval by the Department of the construction plans pursuant to
Subpart E of this Part,
or that clarification of the notice of intent to
construct information is needed.
[510 ILCS 77/11(b)]
2) The Department shall, within 15 calendar days after receipt of
the clarification information submitted pursuant to this subsection or
subsection (b)(1) of this Section, notify the owner or operator that
construction may begin only after receipt and approval by the Department of the
construction plans pursuant to Subpart E of this Part, or that clarification of
the notice of intent to construct information is needed.
3) Within 15 calendar days after receipt by the Department of
information that completes the notice of intent to construct form, the
Department shall issue an acknowledgement of setback compliance to the owner or
operator if the Department has determined that the owner or operator has
complied with the setback and notice of intent to construct requirements of
this Part.
4) Within 10 calendar days after receipt of the Department's
acknowledgment pursuant to subsection (b)(3) of this Section, the owner or
operator shall mail by certified mail, return receipt requested, a copy of the
complete notice of intent to construct to the owners of the property located
within the setback areas. The owners of the property located within the
setback areas are presumed, unless established to the contrary, to be the
persons shown by the current tax collector's warrant book to be the party in
whose name the taxes were last assessed.
5) Construction shall not begin until the acknowledgment of
setback compliance has been issued by the Department to the owner or operator
pursuant to this Section, copies of the complete notice of intent to construct
form have been mailed to owners of property within the setback areas, and
construction plans for the livestock waste handling facility have been approved
by the Department.
c) For livestock management or livestock waste handling
facilities that are subject to the public informational meeting process as
outlined in Section 12 of the Livestock Management Facilities Act [510 ILCS
77/12] and Subpart D of this Part, the following procedures shall be followed:
1) Within 15 calendar days after receipt of a notice of intent to
construct form by the Department, the Department shall review the form and
notify the owner or operator that all information regarding the form has been
submitted or that clarification is needed. Upon receipt of any clarification
information, the Department shall, within 15 calendar days after receipt of the
information, review the information and notify the owner or operator that all
information has been submitted or that additional clarification is needed.
2) If a public informational meeting is not held, the Department
shall issue an acknowledgment of setback compliance to the owner or operator
within 10 calendar days after the expiration of the time period for the county
board to request a meeting pursuant to Section 900.403 of this Part if the
Department has determined that the owner or operator has complied with the
setback and notice of intent to construct requirements of this Part. If a
public informational meeting is held, the Department shall issue an
acknowledgment of setback compliance to the owner or operator within 10
calendar days after receipt of the county board's recommendation pursuant to
Section 900.406 of this Part if the Department has determined that the owner or
operator has complied with the setback and notice of intent to construct
requirements of this part.
3) Within 10 calendar days after notification by the Department
to the owner or operator that all information has been submitted pursuant to
subsection (c)(1) of this Section, the owner or operator of the proposed
facility shall mail by certified mail, return receipt requested, a copy of the
complete notice of intent to construct form to the owners of property located
within the setback areas. The owners of the property located within the
setback distances are presumed, unless established to the contrary, to be the
persons shown by the current collector's warrant book to be the party in whose
name the taxes were last assessed.
4) Construction shall not commence until the acknowledgment of
setback compliance has been issued by the Department and the provisions set
forth in Sections 900.407 and 900.409 of this Part have been met.
5) Upon receipt of a complete notice of intent to construct form
or information that completes a notice of intent to construct form, the
Department shall provide notice to the county board of the county which the
facility is to be located and to the public pursuant to Subpart D of this Part.