8 Ill. Adm. Code 900.703
Level of Surety
Section 900
Section 900.703 Level of
Surety
a) The level of surety is determined by the following formula:
Level of
Surety = (V x CF) + EC
where:
V
=
Volume of the lagoon as
constructed or modified, in cubic feet, including the freeboard volume
CF
=
Cost factor determined
pursuant to subsection (b) of this Section
EC
=
Engineering contingency
determined under subsection (c) of this Section
b) The cost factor is obtained from the following:
1) Through December 31, 2002, the cost factor is 10 cents per
cubic foot of lagoon volume.
2) On and after January 1, 2003 through December 31, 2007, the
cost factor is 12 cents per cubic foot of lagoon volume.
3) On and after January 1, 2008, the cost factor is 15 cents per
cubic foot of lagoon volume.
c) The engineering contingency is equal to 10% of (V x CF).