92 Ill. Adm. Code 16.160
Notice of Construction or Alteration of Any Structure
Section 16.160 Notice of Construction or Alteration of
Any Structure
a) Construction
or Alteration Requiring Notice (14 CFR 77.13, effective October
1, 2002). Each person or sponsor proposing any of the following construction
or alterations of any structure on or in the vicinity of the airports listed in
Section 16.Appendix A shall notify the Division (see subsection (b) of this
Section), for objects on airport property, or the FAA, for objects off airport
property.
1) Any
construction or alteration of more than 200 feet in height above the natural
ground level at its site.
2) Any
construction or alteration of a height greater than an imaginary surface
extending outward and upward at one of the following slopes:
A) 100:1
for a horizontal distance of 20,000 feet from the nearest point of the nearest
runway of the airport, with at least one runway more than 3,200 feet in actual
length.
B) 50:1
for a horizontal distance of 10,000 feet from the nearest point of the nearest
runway of the airport, with the longest runway not more than 3,200 feet in
actual length.
C) 25:1
for a horizontal distance of 5,000 feet from the nearest point of the nearest
landing and takeoff area of each heliport/vertiport.
3) Any
highway, railroad, or other traverse way for mobile objects, of a height that
would exceed a standard described in subsection (a)(1) or (a)(2) of this
Section, if adjusted upward: 17 feet for an Interstate Highway that is part of
the National System of Military and Interstate Highways where overcrossings are
designed for a minimum of 17 feet vertical distance; 15 feet for any other
public roadway; 10 feet or the height of the highest mobile object that would
normally traverse the road, whichever is greater, for a private road; 23 feet
for a railroad; and for a waterway or any other traverse way not previously
mentioned, an amount equal to the highest mobile object that would normally
traverse it.
4) Any
construction or alteration that exceeds a standard of the Act or of this Part.
b) Form and Time of Notice
1) Each
person required to notify the Division under subsection (a) of this Section
shall forward one completed FAA Form 7460-1, Notice of Proposed Construction or
Alteration, to the Illinois Department of Transportation, Division of
Aeronautics, Capital Airport, 1 Langhorne Bond Drive, Springfield, Illinois
62707-8415.
2) Notice
must be submitted at least 30 calendar days before the date the proposed
construction or alteration is to begin.
3) In
the case of an emergency involving essential public services, public health, or
public safety that requires immediate construction or alteration, the 30
calendar day requirement in subsection (b)(2) of this Section does not apply
and notice may be communicated to the Division by telephone (217-785-8500),
telegraph, facsimile (217-785-4533), or other expeditious means, with a
completed FAA Form 7460-1 submitted to the Division within 5 calendar days after
the emergency. For example, an emergency could include breaks in sewer lines,
gas mains or power lines.
c) Acknowledgment of Notice
1) The
Division will acknowledge in writing the receipt of a notice submitted under
subsection (a) of this Section within 30 calendar days after receipt of the
notice.
2) The
acknowledgment will state whether a study of the proposed construction or
alteration has resulted in a determination that the construction or alteration:
A) will require lighting or
marking;
B) will not be in violation
of this Part or Departmental standards;
C) will
require supplemental information (e.g., certified engineering/survey data from
a professional engineer, architect or surveyor on the certifier’s letterhead
regarding the proposed site location and height) (Once the supplemental
information has been reviewed by the Division, a second acknowledgment will be
sent to the person or sponsor and a determination concerning the proposed
construction or alteration will again be made pursuant to subsection (c) of
this Section.);
D) will require a permit
from the Division (see Section 16.170);
E) will require a variance
from the Division (see Section 16.180); or
F) will be acceptable, as
submitted.
d) Compliance with Acknowledgment. The
person or sponsor that notifies the Division of the construction or alteration
of a structure shall have the sole responsibility to comply with the
requirements set forth in the Division's acknowledgement as described in
subsections (c)(2)(A), (C), (D) and (E) of this Section.