92 Ill. Adm. Code 544.40
Definitions
Section 544
Section 544.40 Definitions
For purposes of this Part:
"Department"
means the Department of Transportation, and "State" means the State
of Illinois.
"Energy
Charges" include the costs of supplying electrical energy for the
operation of the signals.
"Installation"
includes the costs involved in the preparation of plans and performing
construction inspection, as well as the construction costs of installing the
traffic signals at an intersection.
"Intersection
Approaches" include both legs of one-way streets as if they were carrying
two-way traffic.
"Local
Agency" refers to county, township, or municipal governments.
"Maintenance"
includes costs of routine maintenance on the signals, as well as emergency
repairs in the event of malfunction of the controller or physical damage
resulting from accidents, severe weather, or vandalism.
"Modernization"
includes all engineering costs, as well as the construction costs of altering
or modifying an existing signal installation, either to bring it into
conformance with the current Illinois Manual on Uniform Traffic Control Devices
(92 Ill. Adm. Code 546), to satisfy a need for improvement in the operation of the
signals, or to correct an accident problem at an intersection. The
modernization may include altering the operation through changes in sequencing
and timing or modification of the physical layout of the signals.
"State
Highway" refers to any highway, regardless of whether or not it is a
marked route, that is maintained by State forces or maintained by others, with
total or partial reimbusement by the State.