92 Ill. Adm. Code 600.25
Application
Section 600.25 Application
a) Before
applying for funding, applicants shall:
1) Register
in the grantee portal;
2) Complete
the internal control questionnaire; and
3) Meet the
criteria to become pre-qualified under GATA.
b) Applications
shall include:
1) A
map, sketch, or other depiction of the project site and its surrounding area,
including all transportation access facilities;
2) A
project layout or conceptual drawing, schematic plans, surrounding reports
related to the project, such as environmental or development reports;
3) Documentation
showing whether the proposed project is consistent with development plans by
local government, private sector local development plans approved by local
governments (e.g., zoning or permitting), or the comprehensive plan of the
local government, if plans have been adopted. The only plans required to be
submitted are those within the area of the public port district;
4) A
schedule of tasks and goals for project accomplishment;
5) If a
local match is required under Section 600.20(c), documentation of the source of
the required matching funds with reasonable assurances that these funds are
available and enough to complete the project;
6) A
financial summary, on a form prescribed by the Department, that identifies the
total cost for the project and the amount being requested from the Program;
7) The
port's master planning documents or assurance that a port master plan is to be
completed;
8) A
completed standard GATA application form;
9) A
completed conflict of interest form;
10) A
completed programmatic risk assessment;
11) The
following documentation:
A) A
document identifying all the current members of the port's board and the
chairperson and officers of the board, if any; and
B) The
board resolution indicating the approval to apply for the grant. The resolution
shall be signed by the board's chairperson, treasurer, secretary, or a board
member authorized to sign and shall indicate the number of board member votes
for and against that approval; and
12) Any
additional information required by the NOFO issued by the Department.
c) Applications
shall be due 60 days after the date the NOFO is published.
d) Applications
shall be electronically filed with the Department as outlined in the NOFO.