92 Ill. Adm. Code 800.440
Force Majeure
Section 800
Section 800.440 Force
Majeure
In the event that the recipient
or a contractor is delayed, hindered in, or prevented from the performance of
any act required by the contract by reason of any of the following:
a) strikes, lockouts, labor troubles;
b) unduly harsh weather conditions, not including foreseeable and
ordinary adverse weather conditions such as rain and snow, which prevent the
normal performance of the rehabilitation project;
c) inability to procure materials;
d) failure of power;
e) riots, insurrection, or war; or,
f) any Act of God;
the time of performance of such
delayed party may be extended for a time period equal to such delay.