329 IAC 11-5-7
329 IAC 11-5-7 Existing facilities requiring a permit
Cite as Ind. Admin. Code tit. 329, r. 11-5-7
Sec. 7. (a) A solid waste processing facility described in section 1(b)(2) of this rule that is operating on the effective date of the 2007
amendments to this article must do the following:
(1) Notify the department within thirty (30) days after the effective date of the 2007 amendments to this article of one (1) of the
following:
(A) A permit application will be submitted.
(B) The facility will cease operation within sixty (60) days.
(2) If the facility will continue to operate, submit a complete application as required by 329 IAC 11-9-1 and 329
IAC 11-9-2 within sixty (60) days after the effective date of the 2007 amendments to this article.
(b) The facility must be operated under the applicable requirements of this article until the:
(1) permit for the facility is effective; or
(2) facility ceases operation.