170 IAC 4-1-12
170 IAC 4-1-12 Customer requests for tests; application to commission
Cite as Ind. Admin. Code tit. 170, r. 4-1-12
Sec. 12. (a) Upon application of any customer to the commission, and at the discretion of the commission, a test shall be made of the
customer's watthour meter by the public utility or its contractor under the supervision of an employee of the commission. The commission shall
promptly notify the public utility of any application. No fee shall be payable by the customer for the test, except as may be charged under section
11(b) of this rule.
(b) Upon application of any customer to the commission, and at the discretion of the commission, an electric demand test shall be made
upon the customer's electric load by the public utility or its contractor under the supervision of an employee of the commission. The commission
shall promptly notify the utility of any application. The requested test shall be made as soon as practicable after receipt of the application and under
exactly similar conditions of installation and operation as may be mutually agreed upon, in writing, by the customer and the public utility. No fee
shall be payable by the customer for the test, except as may be charged under section 11(b) of this rule.
(c) This section shall not interfere with the practice of a utility in its tests of meters except that, upon receiving notice of a written
application to the commission by a customer for a test, the utility shall not:
(1) remove;
(2) interfere with; or
(3) discard;
the customer's meter until completion of the test without the prior written consent of the customer, unless the removal of the meter is required
in order to perform the requested test.