Sec. 13. A facility construction permit may be revoked or modified by the department for any of the following causes: (1) Violation of a law or rule applicable to the facility, or any other applicable sanitation, health, siting, or pollution control rules or ordinances existing at the time of application. (2) Violation of any limitation, term, or condition contained in the construction permit. (3) Failure to disclose all facts relevant to construction and use of the facility that might adversely impact health, surface water, or ground water. (4) Any misrepresentation made to obtain the construction permit. (5) Any other change, situation, or activity relating to use of the facility that, in the judgment of the department, is not consistent with the purposes of this rule or a law or rule applicable to the facility.
410 IAC 6-12-13: 410 IAC 6-12-13 Construction permit revocations and modifications | Justis AI