170 IAC 4-6-16

170 IAC 4-6-16 Ratemaking treatment; preconstruction costs of clean coal technology

Last amended: 2025Year: 2027Length: 71 wordsOfficial source

Cite as Ind. Admin. Code tit. 170, r. 4-6-16

Sec. 16. A utility that engages in one (1) or more clean coal technology projects may classify preconstruction costs related to the projects as operating expenses and record these expenses in a deferred account. The utility may seek ratemaking treatment of the preconstruction costs in a general rate case before the commission. If the utility classifies preconstruction costs as operating expenses, the utility shall not record the same amounts as CWIP.