170 IAC 4-9-5
170 IAC 4-9-5 Notice requirements for line upgrades
Cite as Ind. Admin. Code tit. 170, r. 4-9-5
Sec. 5. (a) At least sixty (60) calendar days prior to a utility changing a distribution or transmission line to a higher voltage level, the utility
must give notice to the affected customer if the change in the line will change the area in which vegetation management will be necessary as a result
of safe clearance requirements.
(b) Notice shall be provided in the same manner as in section 4(b) of this rule.
(c) Notice shall include, at minimum, the following information:
(1) The fact that line upgrades are scheduled to occur.
(2) An explanation of what line upgrades are.
(3) An explanation as to why line upgrades are necessary for safe and reliable electric service.
(4) The fact that nonproperty owners living or working on the property and receiving the notice are strongly encouraged to notify the
property owner as soon as possible that line upgrades are scheduled to occur.
(5) The estimated date that line upgrades are scheduled to occur.
(6) The estimated length of time construction will continue.
(7) New vegetation restrictions on the property as a result of the line upgrades.
(8) Changes to the property owner's easement or right of way as a result of the line upgrades.
(9) Contact information, including, at a minimum, a telephone number for an authorized utility representative who is able to answer
customer inquiries related to line upgrades.