170 IAC 5-5-2.3
170 IAC 5-5-2.3 Positive response to excavators of supplied location information
Cite as Ind. Admin. Code tit. 170, r. 5-5-2.3
Sec. 2.3. (a) An operator of a pipeline facility shall provide an affirmative electronic response to the association in the manner directed
by the association when the operator has provided the marking information in response to an 811 ticket.
(b) The association shall make available the operator's response under subsection (a) to the person responsible for the excavation or
demolition.
(c) An operator of a pipeline facility that does not provide the affirmative response required under subsection (a) violates IC 8-1-26-18(j)(1). If IC 8-1-26-18(j) otherwise applies, the operator is subject to the penalty specified in IC 8-1-26-18(j).