675 IAC 12-4-7
675 IAC 12-4-7 Application of changes in rules of commission to particular construction projects
Cite as Ind. Admin. Code tit. 675, r. 12-4-7
Sec. 7. (a) Construction projects for which design releases must be obtained under 675 IAC 12-6 shall be done in compliance
with the applicable rules of the commission in effect on the date the plans and specifications were filed with the division notwithstanding the repeal
or amendment of any rule before the date the construction work is actually done. Accordingly, any enforcement action taken by the division
concerning such construction shall appropriately cite the rules of the commission in effect at the time of the filing of the plans and
specifications.
(b) Notwithstanding subsection (a), the construction work may be done in accordance with any rule of the commission that takes effect
subsequent to the filing of the plans and specifications and before the actual construction work being done, provided that an appropriate addenda
and revision design release are issued under 675 IAC 12-6-18.
(c) Construction that is exempt from the design release requirements of 675 IAC 12-6, but is not exempt from the application
of the rules of the commission, shall be done in compliance with the rules of the commission in effect on the date the construction work is actually
done. Recognizing that:
(1) the rules may change during the course of construction on a particular project; and
(2) uncertainty may exist as to when particular work was actually done;
there shall be a rebuttable presumption that all construction for such an exempt project is done on the date the construction begins. The scope
of this subsection includes construction on Class 1 structures exempted from the design release requirements by 675 IAC 12-6-4 and
construction on Class 2 structures.
(d) This section does not apply to applications of the rules of the commission not related to new construction.