675 IAC 15-1.3-8
675 IAC 15-1.3-8 Seal of acceptance; reporting use
Cite as Ind. Admin. Code tit. 675, r. 15-1.3-8
Sec. 8. (a) The manufacturer shall certify in an affidavit that a seal of acceptance purchased from the office of the state building commission
[sic., commissioner] was not affixed to an industrialized building system or mobile structure that did not comply with the rules of the
commission.
(b) The manufacturer shall submit a monthly seal of acceptance report for the previous month. This report is required to be submitted even
if the manufacturer did not apply any seals in the previous month. This report shall be submitted to the office of the state building commissioner
on forms provided by the office of the state building commissioner.
(c) The manufacturer's monthly report shall be filed with the office of the state building commissioner no later than the tenth day of the
following month.
(d) The manufacturer shall maintain a copy of the monthly reports for a minimum of five (5) years.