25 IAC 9-5-3
25 IAC 9-5-3 Review process for noncompliance
Cite as Ind. Admin. Code tit. 25, r. 9-5-3
Sec. 3. (a) Upon the notification of the determination of noncompliance, the prime or subcontractor may submit a written letter of protest
on the grounds that such findings are:
(1) arbitrary, capricious, or an abuse of discretion;
(2) conducted contrary to a constitutional, statutory, or regulatory provision;
(3) made without observance of a procedure required by law;
(4) in error or based on mistake; or
(5) not objectively formulated, may have been collusive, or may have been submitted in bad faith.
(b) The burden of challenging the findings of the department under section 2 of this rule remains with the petitioner.
(c) The letter of protest must be received by the department not more than ten (10) business days (as defined by the state work calendar)
from the notification of findings.
(d) Letters of protest must state, with specificity, all grounds for relief. Protest letters that do not allege a ground for relief as described
in subsection (a) may be rejected by written notification from the department. All letters of protest must be submitted to the IVOSB protest
coordinator via electronic mail or to:
Indiana Department of Administration
Procurement Division
Indiana Government Center South
402 West Washington Street, Room W478
Indianapolis, IN 46204
The department will respond in writing to a letter of protest in a timely manner.
(e) Within five (5) days of receiving the department's written response to a letter of protest, the petitioner may submit a request for appeal
to the commissioner's designee. The request for appeal must be in writing and may not state grounds for relief that were not raised in the original
letter of protest.