80 IAC 7-1-44

80 IAC 7-1-44 "Substantial completion" defined

Last amended: 2022Year: 2027Length: 57 wordsOfficial source

Cite as Ind. Admin. Code tit. 80, r. 7-1-44

Sec. 44. "Substantial completion" means the condition of a commission work when it is sufficiently completed, in accordance with the contract documents as modified by any completed change orders agreed to by the parties, so that the commission can occupy or take possession of the commission work and use it as it is intended to be used.
80 IAC 7-1-44: 80 IAC 7-1-44 "Substantial completion" defined | Justis AI