80 IAC 9-4-1

80 IAC 9-4-1 Method of awarding contracts; approval of contract documents

Last amended: 2022Year: 2027Length: 85 wordsOfficial source

Cite as Ind. Admin. Code tit. 80, r. 9-4-1

Sec. 1. (a) Commission works contracts must be awarded under section 2 of this rule unless another method is authorized under this rule. (b) At the discretion of the commission or commission representative, a duly certified or registered architect or licensed engineer may be utilized to approve the contract documents for a commission works project. A consulting engineer or architect may be retained by the commission by a professional services contract for the purpose of assisting in the administration of the provisions of this article.
80 IAC 9-4-1: 80 IAC 9-4-1 Method of awarding contracts; approval of contract documents | Justis AI