80 IAC 9-4-4
80 IAC 9-4-4 Performance of commission works projects by employees of the commission
Cite as Ind. Admin. Code tit. 80, r. 9-4-4
Sec. 4. If the estimated cost of a commission works project, including labor and materials, is less than one hundred fifty thousand dollars ($150,000), the project may be performed by appropriate employees of the commission without awarding a commission works contract under section 2 of this rule.