312 IAC 25-4-7

312 IAC 25-4-7 Permit applications; format and contents review

Last amended: 2025Year: 2027Length: 96 wordsOfficial source

Cite as Ind. Admin. Code tit. 312, r. 25-4-7

Sec. 7. Each application for a surface coal mining and reclamation permit under a regulatory program shall be reviewed as to its completeness prior to formal review and shall include the following: (1) This completeness review shall be completed not later than fifteen (15) working days after such permit is submitted. (2) The director shall contact the applicant not later than five (5) working days after a permit is reviewed for completeness and shall state: (A) which portions of the permit application are incomplete; and (B) those conditions and information requirements necessary to complete the application.
312 IAC 25-4-7: 312 IAC 25-4-7 Permit applications; format and contents review | Justis AI