327 IAC 3-6-7
327 IAC 3-6-7 Issuance requirements for sanitary sewer construction permits
Cite as Ind. Admin. Code tit. 327, r. 3-6-7
Sec. 7. The application for any construction permit required by this article shall be denied unless the applicant submits evidence of the
following:
(1) The peak daily flow rate, in accordance with section 11 of this rule generated in the area that will be collected by the project
system, will not cause overflowing or bypassing in the collection system from locations other than NPDES authorized discharge
points.
(2) Sufficient capacity exists in the receiving water pollution treatment/control facility to treat the additional daily flow.
(3) The receiving water pollution treatment/control facility will remain in compliance with applicable NPDES permit effluent
limitations.
(4) The sanitary sewer or collection system that is the subject of the construction permit application is to connect to a water
treatment/control facility that has been completed and put into operation.
(5) The proposed collection system does not include new combined sewers or a combined sewer extension to existing combined
sewers.