327 IAC 4-1-7

327 IAC 4-1-7 Grounds for termination of sewer connection ban

Last amended: 2026Year: 2027Length: 72 wordsOfficial source

Cite as Ind. Admin. Code tit. 327, r. 4-1-7

Sec. 7. A sewer connection ban may be terminated by the commissioner when either of the following exist: (1) A demonstrated wastewater treatment facility improvement to meet applicable NPDES permit limitations has been completed. (2) It is demonstrated to the satisfaction of the commissioner that an existing hydraulic/organic overloaded condition has been or will be discontinued for a continuous period of twelve (12) months from the date additional connections will be made.
327 IAC 4-1-7: 327 IAC 4-1-7 Grounds for termination of sewer connection ban | Justis AI