LAC 43:XIII.2906

LAC 43:XIII.2906. Transmission Lines: Leakage Surveys [49 CFR 192.706]

Last amended: 2004Year: 2026Length: 103 wordsOfficial source

Cite as La. Admin. Code tit. 43, pt. XIII, § 2906

A. Leakage surveys of a transmission line must be conducted at intervals not exceeding 15 months, but at least once each calendar year. However, in the case of a transmission line which transports gas in conformity with §2725 without an odor or odorant, leakage surveys using leak detector equipment must be conducted: [49 CFR 192.706] 1. in Class 3 locations, at intervals not exceeding seven and one-half months, but at least twice each calendar year; and [49 CFR 192.706(a)] 2. in Class 4 locations, at intervals not exceeding four and one-half months, but at least four times each calendar year. [49 CFR 192.706(b)]