LAC 43:XIII.7913

LAC 43:XIII.7913. Auxiliary Power Sources [49 CFR 193.2613]

Last amended: 2018Year: 2026Length: 52 wordsOfficial source

Cite as La. Admin. Code tit. 43, pt. XIII, § 7913

A. Each auxiliary power source must be tested monthly to check its operational capability and tested annually for capacity. The capacity test must take into account the power needed to start up and simultaneously operate equipment that would have to be served by that power source in an emergency. [49 CFR 193.2613]