LAC 7:XIII.793
LAC 7:XIII.793. Watermelon Seed Certification Standards
Cite as La. Admin. Code tit. 7, pt. XIII, § 793
A. Field Inspection
1. The initial inspection will be made before the first blooms are open. At this time, volunteer plants and citron must be removed from the field to be certified and the isolation zone by the grower.
2. The second inspection will be made when the melons are ready to harvest. The presence of any citron plants within 2,640 feet of a unit entered for foundation or registered classes or within 1,320 feet of a unit entered for certified class will disqualify the unit for certification.
B. Field Standards
Factor | Foundation | Registered | Certified
Land Requirement | 1 yr.
Isolation | 2,640 ft. | 1,320 ft.
At Harvest Time:
Citron | None
White Heart Fruits | None | 2.00% | 5.00%
Total Off-Type Plants or Varietal Mixtures | None | 2 Plants per Acre
*Plants Free from Fusarium Wilt | 93.00% | 90.00%
Plants Free from Anthracnose | 95.00% | 90.00%
*Applies to wilt-resistant varieties only
C. Seed Standards
Factor | Foundation | Registered | Certified
Pure Seed | 98.00%
Inert Matter | 2.00%
Other Crops | None | 2 seed/lb. | 5 seed/lb.
Other Varieties | None | 4 seed/lb.
Citron | None
Weed Seeds | None | 0.05%
Germination | 80.00%