LAC 13:I.903
LAC 13:I.903. Advance Requirements
Cite as La. Admin. Code tit. 13, pt. I, § 903
A. The applicant shall submit an "advance" with LED through the department’s online portal prior to the project start date. A non-refundable fee shall be paid online with the submission of the advance form in accordance with R.S. 36:104.
1. The project start date shall not exceed 12 months after the advance filing date. Dates may be amended by the applicant if the written request is made within 90 days of the estimated project start date. In no instance shall the project start date exceed 12 months after the advance filing date.
B. LED reserves the right to request additional information for the advance. The document will not be considered officially received and accepted until the appropriate fee and information is submitted.