LAC 33:V.30266
LAC 33:V.30266. Construction Records [49 CFR 195.266]
Cite as La. Admin. Code tit. 33, pt. V, § 30266
A. A complete record that shows the following must be maintained by the operator involved for the life of each pipeline facility: [49 CFR 195.266]
1. the total number of girth welds and the number nondestructively tested, including the number rejected and the disposition of each rejected weld; [49 CFR 195.266(a)]
2. the amount, location, and cover of each size of pipe installed; [49 CFR 195.266(b)]
3. the location of each crossing of another pipeline; [49 CFR 195.266(c)]
4. the location of each buried utility crossing; [49 CFR 195.266(d)]
5. the location of each overhead crossing; [49 CFR 195.266(e)]
6. the location of each valve and corrosion test station; [49 CFR 195.266(f)]
7. for pipelines transporting carbon dioxide, the location of each weighted pipe or other item connected to the pipe.