301 CMR 11.13
Emergency Action
(1) Commencement of Project for Emergency Action and Initial ENF. In the rare case when
Commencement of a Project is essential to avoid or eliminate an imminent threat to
environmental resources or quality or public health or safety, the Proponent may undertake
Commencement of the Project without prior due compliance with MEPA and 301 CMR 11.00
provided that the Proponent shall make all reasonable efforts to obtain the prior written approval
of the Secretary. The Proponent shall limit any emergency action taken without prior due
compliance with MEPA and 301 CMR 11.00 to the minimum action necessary to avoid or
eliminate the imminent threat. The Proponent shall file an initial ENF describing the Project in
as much detail as is then known within ten Days of Commencement of the Project. The initial
ENF shall describe all measures taken to avoid or minimize potential environmental impacts
from the emergency action, describe any additional measures to be taken to mitigate potential
environmental impacts from the emergency action, and list any Agency to which the Proponent
provided prior notification of, or from which the Proponent received prior approval for, the
emergency action. Within the earlier of 60 Days of Commencement of the Project or when the
threat is no longer imminent, the Proponent shall undertake full due compliance with MEPA and
301 CMR 11.00 by filing an amended or substitute ENF or any other review document that the
Secretary may require after reviewing the initial ENF.
(2) EIR after Emergency Action. An EIR for a Project on which the Proponent undertook
emergency action shall describe specific alternatives to the emergency action, the necessary
duration of the emergency action, and the appropriateness or necessity of undertaking similar
action in similar future circumstances.
(3) Programs or Projects Not Considered EmergencyAction. Anyprogram, regulations, policy,
or other Project implemented or undertaken to deal with future emergencies, or periodic
recurrence of an emergency condition, shall not be considered an emergency action.