310 CMR 10.06
Emergencies
(1) Unless authorized by a Severe Weather EmergencyDeclaration issued by the Commissioner
pursuant to 310 CMR 10.06(8), any person requesting permission to do an emergency project
shall specify why the project is necessary for the protection of the health or safety of the citizens
of the Commonwealth and what agency of the Commonwealth or subdivision thereof is to
perform the project or has ordered the project to be performed. If the project is certified to be
an emergency by the conservation commission or the Commissioner, the certification shall
include a description of the work which is to be allowed and shall not include work beyond that
necessary to abate the emergency. A site inspection shall be made prior to certification.
(2) An emergency certification shall be issued only for the protection of public health or safety.
(3) The time limitation for performance of emergency work shall not exceed 30 days, or 60 days
for Immediate Response Actions approved by the Bureau of Waste Site Cleanup (BWSC) of the
Department of Environmental Protection in accordance with the provisions of 310 CMR
40.0410: Immediate Response Actions, unless written approval of the Commissioner is obtained.
(4) A copy of an emergency certification shall be sent to the Department when it is issued by
a conservation commission, and to the conservation commission when it is issued by the
Department.
(5)
The Department may, on its own motion or at the request of any person, review: an
emergency certification issued by a conservation commission and any work permitted
thereunder; a denial by a conservation commission of a request for emergency certification; or
the failure by a conservation commission to act within 24 hours of a request for emergency
certification. Such review shall not operate to stay the work permitted by the emergency
certification unless the Department specifically so orders. The Department's review shall be
conducted within seven days of: issuance by a conservation commission of the emergency
certification; denial by a conservation commission of the emergency certification; or failure by
a conservation commission to act within 24 hours of a request for emergency certification. If
certification was improperly granted, or the work allowed thereunder is excessive or not required
to protect the health and safety of citizens of the Commonwealth, the Department may revoke
the emergency certification, condition the work permitted thereunder, or take such other action
as it deems appropriate.
10.06: continued
(6) Agricultural Emergencies
(a) Notwithstanding the provisions of 310 CMR 10.06(1) through (4), any person may
undertake work for the emergency agricultural activities described in 310 CMR 10.06(6)(g)
when necessary to:
1. eliminate an imminent threat to land in agricultural use;
2. restore land in agricultural use that has been damaged due to a storm or other sudden,
unforeseen event; or
3. provide an emergency agricultural water source when the existing agricultural water
source suddenly and unforeseeably has been rendered unusable or unavailable.
4. eradicate an infestation of Asian longhorned beetles (Anoplophora glabripennis) in
response to an order or regulation issued by the United States Department of Agriculture
(USDA) pursuant to 7 USC §§ 7701 et seq. (the Plant Protection Act), or the Department
of Conservation and Recreation (DCR) pursuant to M.G.L. c. 132, § 11.
(b) Written notice of any work undertaken as an emergency activity under 310 CMR
10.06(6) must be received by the conservation commission and mailed to the Department
within three days after the work has commenced or within three days after the end of the
emergency event, whichever is sooner. Such notice shall state the name of the person
performing the work, the name of the property owner (if different), the property and the
location on the property where the work is to be performed, the exact nature of the
emergency and of the work which is to be performed, and when the work was begun and
when it is expected to be completed. The commission may, at its discretion, conduct a site
visit to view the work being performed under such notice and to confirm that the information
in the notice is correct.
(c) When an emergency is caused by a storm, any work undertaken as an emergency activity
under 310 CMR 10.06(6) must commence within 30 days following the storm event which
caused the agricultural emergency.
(d) Any work undertaken as an emergency activity under 310 CMR 10.06(6) shall be
completed within 30 days from the commencement of such work unless written approval for
a later completion date is given by the Commissioner.
(e) No work under 310 CMR 10.06(6) shall be allowed within estimated habitat which is
indicated on the most recent Estimated Habitat Maps of State-listed Rare Wetlands Wildlife
published by the Natural Heritage and Endangered Species Program of the Massachusetts
Division of Fisheries and Wildlife.
(f) Work under 310 CMR 10.06(6) shall not fill or dredge a Salt Marsh.
(g) Only the following emergency activities are allowed under 310 CMR 10.06(6)(a):
1. The installation of stream bank stabilization measures, provided that:
a. such activity is carried out in accordance with Soil Conservation Service best
management practices;
b. no more than 100 linear feet of bank are altered per storm event, and no more
than 200 linear feet of new rip rap or gabions are placed on the bank of a stream
under 310 CMR 10.06(6) cumulatively; and
c. after the 200 foot threshold has been reached the placement of additional rip rap
or gabions following future storm events shall require the filing of a Notice of Intent.
2. The removal of storm debris, including trees, brush, branches, and cobbles, that were
deposited in a stream channel during the storm event, provided that:
a.
after the material is removed it is not placed on a bank or in a Bordering
Vegetated Wetland;
b. Soil Conservation Service best management practices are followed; and
c. removal of material from a stream is limited to 100 linear feet per storm event.
3.
The development of an emergency agricultural water source where the existing
agricultural water source suddenly has been rendered unusable because of contamination,
sudden diversion, or other unforeseen circumstances. Where an emergency agricultural
water supply is required:
a. the work shall be conducted so that impacts to Bordering Vegetated Wetland are
minimized and all impacts, including excavation, access, and any other alterations
to Bordering Vegetated Wetland, shall not exceed 2,000 square feet;
b. the size of the water supply shall be limited to that necessary to provide the
amount of water required to abate the emergency, but not to exceed 2,000 square feet;
10.06: continued
c. a Notice of Intent shall be filed if the agricultural water supply is to be used for
more than 60 days, in which case the agricultural water supply shall comply with
existing performance standards under 310 CMR 10.53(3)(a), (b), and (g); and
d. all work shall comply with the Water Management Act, M.G.L. c. 21G.
4. The removal of trees, including stumps, and the application of pesticides to trees and
soil within an area defined by USDA or DCR in an order or regulation to eradicate an
infestation of Asian longhorned beetles, notwithstanding the provisions of 310 CMR
10.06(6)(d) or (e), provided that the work is conducted as follows:
a. The provisions of 310 CMR 10.06(6)(g)4. shall apply to USDA or DCR, if those
agencies are performing eradication work, or to other persons if authorized or ordered
by DCR to undertake eradication activity, in areas subject to regulation under
M.G.L. c. 131, § 40. For the purposes of 310 CMR 10.06(6)(g)4., these agencies or
persons shall be defined as authorized persons. At least 14 days prior to beginning
work in any municipality, an authorized person shall submit to the conservation
commission and MassDEP’s regional office a GIS orthographic photo or map
showing all resource areas in which work is to be conducted within the municipal
boundaries, including wetland or stream crossings to gain access to work areas or
Estimated Habitats for State-listed Rare Wetlands Wildlife, along with a proposed
schedule or phasing plan for the eradication activities. If work is proposed within an
Estimated Habitat, an authorized person shall provide the above described photo or
map to the Natural Heritage and Endangered Species Program (NHESP) at the same
time it is submitted to the conservation commission and MassDEP.
b. At least three days before beginning work at a specific site, an authorized person
shall submit to the conservation commission and MassDEP’s regional office a plan
on a USGS or other map of at least 1=5:000 scale showing the work in the designated
area as well as skid roads, stream and wetland crossings, landings and the general
location of erosion control measures. An authorized person shall provide the name
and contact information of an on-site supervisor responsible for compliance with the
wetland related requirements of the harvest, including maintenance of the erosion
control measures. MassDEP, a designated representative of the conservation
commission and the authorized person shall conduct a site inspection at least 48
hours before beginning the work, to explore access options, proposed activity in
resource areas, erosion controls, and final stabilization with the intent to minimize
wetland impacts, unless MassDEP and the designated representative of the
conservation commission determine, after a review of the plan, that a site visit is not
necessary. If work is proposed within an Estimated Habitat, USDA, DCR or any
person authorized or ordered by DCR to undertake eradication activity shall provide
the above described map to the NHESP and the contact information for an on-site
supervisor at the same time the information is provided to the conservation
commission and MassDEP and shall also provide the NHESP with reasonable
advance notice of any site inspection of the proposed work area.
c. Storage of materials and equipment shall be on paved surface or otherwise stable
surface, outside resource areas, buffer zones, vernal pools, and the Zone I and Zone
A of public water supply sources. Fuels, lubricants or hazardous materials shall not
be stored, transferred between containers or mixed, and machinery shall not be
refueled, in or within 100 feet of a resource area, vernal pool or the Zone I or Zone
A of a public water supply.
d. Landings, access roads, and skid roads shall be located carefully to avoid steep
slopes, resource areas, vernal pools, and stream crossings whenever possible. Access
roads shall be stable and minimize site disturbance including impacts to vegetation,
soil, topography, hydrology and soils.
e. Stream crossings shall be avoided whenever possible. If temporary crossings are
unavoidable, the crossing structures shall be removed at the end of the operation, and
the site, banks, and approaches shall be stabilized. All crossings shall be made at
right angles to the channel, and the approaches to a stream crossing shall be stabilized
continuously both during the logging operation and after completion. At least one
water bar shall be installed directly uphill from a crossing to prevent water moving
down a skid road from reaching a stream. The water bar shall be reinforced as
needed during the course of the work. The approaches may be corduroyed with poles
to prevent rutting and the churning of soil. Erosion controls shall be placed in the
skid road at the approach to a stream crossing at the end of the day.
10.06: continued
f. When operating in a resource area, harvesters shall concentrate skidding in a few
well-defined corridors, use cable and winch as much as possible, and fell trees away
from resource areas to facilitate winching them out. Harvesters shall use best efforts
to avoid damaging non-targeted trees during eradication efforts. Harvesters shall use
brush or corduroy to minimize ground pressure and rutting, shall reduce hitch
volumes to minimize rutting, and shall use Best Management Practices (BMPs) to
minimize sediment transport. Machinery shall not operate in a resource area unless
the ground is dry, frozen, or otherwise stable enough to support it. In some limited
situations where work is proposed in less than stable conditions and where, subject
to approval by the conservation commission or the Department, tree removal requires
heavy equipment operation in wetlands, the equipment shall either have low ground
pressure (<3 psi), or shall not be located directly on wetland soils and vegetation.
Equipment shall be placed on swamp mats that are adequate to support the equipment
in such a way as to minimize disturbance of wetland soil and vegetation.
g. Vehicles and heavy equipment shall not be operated on the banks of water-
bodies. For all work along a stream bank, minimize disturbance and discharge of soil
to the waterway. Stabilization measures shall be implemented including placement
of rock, mulch, seed, erosion control fabric, re-plantings, and/or other measures as
appropriate based upon the area of disturbance. Rip-rap shall not be used unless
MassDEP and the conservation commission determine that other means of
stabilization are not practicable. If stump removal results in bank destabilization,
then a means to stabilize the bank shall be performed.
h.
Effective erosion controls (BMPs) shall be utilized to prevent discharge of
sediments to resource areas, including silt fencing, temporaryberms, stone dikes, and
rip-rap. Brush or slash shall be placed on skid roads and seed where vulnerable to
erosion. Landings shall be smoothed and graded. Exposed soils shall be seeded or
mulched to prevent erosion. Tire tracks and ruts shall be smoothed along the access
path.
i. Upon completion of harvesting, temporary skidder bridges shall be removed, and
the authorized person shall ensure that fords and other stream crossings are left in a
stable and free-flowing condition. All temporary structures (e.g., culverts, bridges)
shall be removed from resource areas. All unnatural debris generated by the
eradication activity such as cans, papers, discarded tires and metal parts shall be
removed. An authorized person shall not be responsible for the removal of any solid
waste or trash that was on the site prior to the eradication effort. Incidental,
remaining wood debris shall be left in place to promote rapid decay. Restore original
grade of disturbed areas.
j. Bare soil in buffer zones shall be reseeded with a fast-growing non-invasive grass
and disturbed wetland soils shall be reseeded with a wetland native seed mix and
wetland species saplings to prevent establishment of invasive species. Reseeding
shall take place within ten days of grading in spring, summer and fall months, or if
grading activity takes place in winter, at the beginning of the following spring.
Erosion control barriers shall be removed as soon as possible once the site is
stabilized, but stabilization and removal shall occur no later than after the first
growing season following completion of the work.
k. MassDEP and a designated representative of the conservation commission may
inspect sites to ensure the effectiveness of erosion control and revegetation and
reseeding efforts. Within one year of eradication efforts, individual sites shall be
inspected by the authorized person, MassDEP and the conservation commission to
determine the adequacy of erosion control and revegetation and reseeding efforts if
a conservation commission and/or MassDEP have reason to believe that erosion
control, reseeding and revegetation efforts at that site have been unsuccessful.
l. Pesticides shall be handled and applied in accordance with the provisions of
333 CMR 12.00: Protection of Groundwater Sources of Public Drinking Water
Supplies from Non-point Source Pesticide Contamination and 13.00: Standards for
Application.
10.06: continued
(7) Notwithstanding any other requirement of 310 CMR 10.06, Immediate Response Actions
receiving oral approval from the Bureau of Waste Site Cleanup (BWSC) of the Department of
Environmental Protection pursuant to 310 CMR 40.0420(2), or initiated up to 24 hours prior to
notification to and oral approval by BWSC pursuant to 310 CMR 40.0420(7) and (8), may
commence before requesting the conservation commission to issue an emergency certification
under 310 CMR 10.06, so long as such request is made within 24 hours after BWSC has orally
approved commencement of the Immediate Response Action. Once a request for emergency
certification has been made pursuant to 310 CMR 10.06(7), work that commenced before such
filing may continue pending a decision on the request by the conservation commission. Such
work may also continue pending a decision on a request for Departmental review unless the
request has not been filed with the Department within one business day of: issuance by the
conservation commission of the emergency certification; denial by a conservation commission
of the emergency certification; or failure by a conservation commission to act within 24 hours
of a request for emergency certification.
(8) In the event of a destructive weather event requiring widespread recovery efforts, debris
cleanup or roadway or utility repair, the Commissioner may issue a Severe Weather Emergency
Declaration that allows emergency-related work necessary for the protection of the health or
safety of the residents of the Commonwealth to occur without filing a Notice of Intent or a
request for an emergency certification or authorization pursuant to 310 CMR 10.06(1) through
(7). The Severe Weather Emergency Declaration shall describe:
(a) the types of work allowed without filing a notice of intent;
(b) any general mitigating measures to condition the work that may be required in
performing such work;
(c) any notification or reporting requirements;
(d) the geographic area of the Declaration's effect; and
(e) the period of time the Declaration shall be in effect which shall not be longer than 90
days, unless extended by the Commissioner.
The Declaration may include other conditions or limitations as deemed appropriate by the
Commissioner. The Commissioner may revise or revoke the Severe Weather Emergency
Declaration as he or she deems appropriate to further recovery efforts and protect public health
and safety. If the Commissioner deems it necessary for the completion of recovery efforts, he
or she may extend the duration of a Severe Weather Emergency Declaration for a period not to
exceed 90 days. An extension may include a revision of the elements listed in 310 CMR
10.06(8)(a) through (d) as deemed appropriate to further recovery efforts. A Severe Weather
Emergency Declaration and any extension, revision, or revocation thereof, shall be sent
electronically to all conservation commissions in the geographic area of the Declaration's effect,
shall be posted on the Department’s website at hhtp://www.mass.gov/eea/agencies/massdep and
shall be made widely available to the general public through appropriate channels for emergency
communications. A Declaration shall not affect the Department's ability to enforce any general
or special law or regulation that is not altered by a Severe Weather Emergency Declaration, or
enforce the terms of such a Declaration.