310 CMR 15.020
Disposal System Construction Permits
(1) No person shall construct, upgrade, modify or expand a system without a Disposal System
Construction Permit which has been issued by the Approving Authority after the site evaluation
set forth in 310 CMR 15.100 through 15.107 has been completed. In the event it is discovered
during installation of the system that site conditions differ from those contained in the site
evaluation and/or the approved design plans, the originally issued Disposal System Construction
Permit is void, installation shall stop, and the applicant shall reapply for a new Disposal System
Construction Permit. Except for subdivisions entitled to M.G.L. c. 111, § 127P protection,
M.G.L. c. 40B comprehensive permit land, and large systems with approved plans or pursuant
to a variance issued by the Department in accordance with 310 CMR 15.414, a Disposal System
Construction Permit shall not authorize increased design flow which would bring the total design
flow to 10,000 gpd or greater. Disposal System Construction Permits shall be in a form
approved by the Department.
(2) Construction of all systems for which a Disposal System Construction Permit application
has been approved by the local Approving Authority and/or the Department shall be completed,
and the Certificate of Compliance obtained within three years of issuance of the final approval.
Unless an extension pursuant to 310 CMR 15.020(3) is issued, the permit, and any variances or
local upgrade approvals from 310 CMR 15.000 allowed therewith, shall expire if the work
authorized by it is not completed within the three-year period.
(3) The local Approving Authority or the Department may issue a written one year extension
to the Disposal System Construction Permit required by 310 CMR 15.020(1) upon written
request of the permittee, filed before the expiration date, and documenting the facts that prevent
completion of the approved system within the time of the original permit. Only one extension
may be granted.
(4) The local Approving Authority shall not issue a Disposal System Construction Permit until
any approval(s) required by the Department pursuant to 310 CMR 15.000 have been issued.
(5) Any person required to obtain a permit pursuant to 310 CMR 15.000 shall complete and
submit the appropriate application forms to the Approving Authority. As part of an application
for a permit or approval, the Approving Authority may require the applicant to provide
information and analyses as it may reasonably require to determine whether such applicant meets
the requirements of 310 CMR 15.000.