310 CMR 19.005
Computation of Time
Unless otherwise specifically provided by law or 310 CMR 19.000, any determination issued
pursuant to 310 CMR 19.000, or any time period prescribed or referred to in 310 CMR 19.000
shall begin with the first day following the act which initiates the running of the time period, and
shall include every calendar day, including the last day of the time period so computed. If the
last day is a Saturday, Sunday, legal holiday, or any other day in which the Department's offices
are closed, the deadline shall run until the end of the next business day. If the time period
prescribed or referred to is six days or less, only days when the offices of the Department are
open shall be included in the computation.