310 CMR 19.041
Authorization to Construct
(1) General. The following shall not be constructed except in accordance with a valid
authorization to construct issued by the Department in writing:
(a) a new or expanded facility for which a permit has been issued;
(b) modifications to a facility for which a permit modification has been issued, except for
a transfer station that is not a C&D waste transfer station; or
(c) a new phase in the case of a landfill being developed in phases.
(2) Filing. The owner or operator shall file a request for an authorization to construct in writing
with the Department in the appropriate Regional Office. However, unless otherwise indicated,
the Department shall consider an application for a solid waste management facility permit or an
application to modify a permit to constitute a request for an authorization to construct.
(3) Issuance. In general, the Department shall issue an authorization to construct when the solid
waste management facility permit or permit modification is issued, except in the case of phased
construction of a landfill where an authorization to construct may be required for each phase and
except where the Department determines that any of the following permits has not been applied
for, as applicable, or granted at the time the solid waste management facility permit is to be
granted:
(a) Massachusetts Surface Water Discharge Permit for point source discharges to surface
waters pursuant to M.G.L. c. 21, § 43 and 314 CMR 3.00: Surface Water Discharge Permit
Program;
(b) ground water discharge permit pursuant to M.G.L. c. 21, § 43 and 314 CMR
5.00: Ground Water Discharge Permit Program;
(c) storm water discharge permit pursuant to M.G.L. c. 21, § 43, and 40 CFR 122 and
314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material,
Dredging, and Dredged Material Disposal in Waters of the United States Within the
Commonwealth;
(d) sewer connection permit for the discharge of collected and or pre-treated leachate into
a municipal sewer system as required by 314 CMR 7.00: Sewer System Extension and
Connection Permit Program;
(e) Federal Water Pollution Control Act section 404 dredge and fill permit relative to
surface water pursuant to the Federal Water Pollution Control Act; and
(f) other local, state and federal permits, approvals or authorizations that are required for
the construction of the facility.
(4) Sunset. If construction of the facility or first phase thereof has not been completed or no
solid waste has been processed or disposed at the facility within three years of the date of
issuance of an authorization to construct the authorization shall expire. The owner or operator
may apply to the Department for an extension of the authorization at any time prior to or after
it expires.
(5) Enforcement. The issuance of an authorization to construct shall not limit the Department's
right to take enforcement action, including, without limitation, the suspension, revocation or
modification of the permit or revocation of the authorization to construct if 310 CMR 19.000 or
any condition of the permit or authorization to construct is violated.
(6) Deed Notice. In accordance with M.G.L. c. 111, § 150A, the owner or operator of a facility
shall record a notice of the authorization to construct permit in the registry of deeds or, if the site
is registered land, in the registry section of the land court for the district wherein the land lies.
The notice shall be captioned "Notice of Authorization to Construct a Solid Waste Facility" and
shall contain a title reference citing the source of title of the land on which the facility is to be
constructed (i.e., the deed with book and page number if recorded land; probate number if
acquired through a probate proceeding; and certificate of title number if registered land).