310 CMR 19.045
Facility Closure and Post-closure
(1) General. Any facility that stops accepting solid waste voluntarily or in accordance with any
permit, authorization or order issued by the Department or a court of competent jurisdiction or
under any other circumstances shall comply with the requirements of 310 CMR 19.045.
(2) Notification of Voluntary Closure. The owner and/or operator shall notify the Department
no later than six months prior to the date that the facility will stop accepting solid waste.
(3) Compliance with Regulations. Closure activities shall be carried out in compliance with
all applicable regulations and the permit. Landfills shall meet the specific closure requirements
established at 310 CMR 19.140: Landfill Closure Requirements.
(4) Completion of Closure. A facility shall be deemed closed on the date of the Department's
written determination that the closure of the facility has been completed in accordance with the
final closure/post-closure plan.