310 CMR 36.19
Determining Permit Tier for an Application
(1) Groundwater Withdrawals – The Department will determine the permit tier for each application
that includes groundwater withdrawals based on:
(a) the applicant’s baseline withdrawal volume(s);
(b) any requested withdrawal volume above the baseline(s); and
(c) an evaluation of the potential change in the biological category or groundwater withdrawal
category during the late summer bioperiod (July through September) in the subbasin(s) from
which the withdrawal is made; and
(d) for proposed withdrawals determined by the Department not to follow an annual demand
curve with highest average daily withdrawals occurring during the late summer bioperiod (July
through September), an evaluation of the potential change in seasonal groundwater withdrawal
category during the bioperiod when the withdrawal will have the maximum impact on streamflow
in the subbasin(s).
Each application that includes a groundwater withdrawal or a withdrawal from both ground and
surface water will be assigned as follows:
Permit Tier 1
The applicant requests no withdrawal greater than baseline.
Permit Tier 2
The applicant requests a withdrawal greater than baseline, but the requested withdrawal will
not result in a change in the biological category, groundwater withdrawal category or seasonal
groundwater withdrawal category of the subbasin(s) from which it is made.
Permit Tier 3
The applicant requests a withdrawal greater than baseline, and the requested withdrawal will
result in a change in the biological category, groundwater withdrawal category or seasonal
groundwater withdrawal category of the subbasin(s) from which it is made.
(2) Surface Water Withdrawals – Applications for permits that include only a surface water
withdrawal will be assigned as follows:
Permit Tier 1
The applicant requests no withdrawal greater than baseline.
Permit Tier 2
The applicant requests a withdrawal greater than baseline.
(3) Applications for permits for water withdrawals in the groundwater-driven water sources (the
southern portion of South Coastal, Cape Cod, Islands, and portions of Buzzards Bay) will be assigned
as follows:
Permit Tier 1
The applicant requests no withdrawal greater than baseline.
Permit Tier 2
The applicant requests a withdrawal greater than baseline.