310 CMR 40.0190
General Requirements for Conducting Response Actions
(1) For each release or threat of release of oil and/or hazardous materials at a disposal site, one
or more Permanent Solutions to the extent feasible shall be implemented by the applicable
deadline to achieve a level of No Significant Risk. No disposal site shall be deemed to have had
all the necessary and required response actions taken for such site unless and until a level of No
Significant Risk exists or has been achieved in compliance with M.G.L. c. 21E and 310 CMR
40.0000.
(2) Permanent Solutions shall be implemented if:
(a) a level of No Significant Risk does not yet exist at the disposal site;
(b) Permanent Solutions are feasible; and
(c) immediate implementation of one or more Permanent Solutions would be more cost-
effective than phased implementation of Temporary Solutions and Permanent Solutions.
(3) At each disposal site, unless a level of No Significant Risk already exists or one or more
Permanent Solutions is feasible and immediate implementation of such Permanent Solutions
would be more cost-effective than phased implementation of Temporary Solutions and
Permanent Solutions, one or more Temporary Solutions shall be implemented to the extent
feasible by the applicable deadline. Such solutions shall eliminate any substantial hazard to
health, safety, public welfare or the environment which is presented by the disposal site or by any
oil and/or hazardous materials at or from the disposal site in the environment.
(4)
If appropriate, Permanent Solutions or Temporary Solutions may be implemented on
portions of a disposal site.
(5)
Where feasible, implementation of a Permanent Solution shall include a measure or
measures designed to reduce to the extent possible the level of oil and/or hazardous materials in
the environment to background.
(6) In determining whether a Permanent Solution will achieve a level of No Significant Risk
during any foreseeable period of time, the criteria and standards set forth in 310 CMR 40.0900
and any current or reasonably foreseeable uses of the site and the surrounding environment that
may be affected by oil and/or hazardous materials at the site or in the surrounding environment
shall be considered.
40.0190: continued
(7)
RPs, PRPs and Other Persons shall employ or engage persons having the appropriate
training, and as required, currently valid licenses or certifications to conduct a response action
at a disposal site.