310 CMR 40.0466
Utility-related Abatement Measure Completion Reports
(1)
A Utility-related Abatement Measure Completion Report shall be submitted to the
Department within 60 days of the completion of all response actions associated with a Utility-
related Abatement Measure.
(2) A Utility-related Abatement Measure Completion Report shall contain, at a minimum, the
following:
(a) a succinct summary of information and data pertaining to the discovery, location and
evaluation of encountered contamination, and of all response actions undertaken and/or
completed;
(b) documentation on the management of Remediation Waste, Remedial Additives and/or
Remedial Wastewater managed at the site; and
(c) details on any proposed or ongoing active or passive remedial systems that will remain
in place at the site.
(3) Except as provided in 310 CMR 40.0466(4), a Utility-related Abatement Measure shall not
be considered complete until all stockpiled/stored Remediation Waste generated as a result of
the Utility-related Abatement Measure is removed from the site pursuant to the provisions of
310 CMR 40.0030.
(4) Remediation Waste may be stored, treated, managed, disposed, recycled or reused at a site
following the submission to the Department of a Utility-related Abatement Measure Completion
Report and Completion Statement only if:
(a) such actions are conducted in conformance with the provisions of 310 CMR 40.0030;
and
(b) a Release Abatement Measure Plan pursuant to the provisions of 310 CMR 40.0440 or
a Remedy Implementation Plan pursuant to the provisions of 310 CMR 40.0870 is submitted
to the Department as an attachment to the Utility-related Abatement Measure Completion
Statement.
(5) Except as provided in 310 CMR 40.0466(6), Utility-related Abatement Measure Completion
Reports shall be submitted to the Department appended to a Completion Statement form
established by the Department for such purposes. The Completion Statement form shall contain:
40.0466: continued
(a) an LSP Opinion on whether the Utility-related Abatement Measure was conducted in
accordance with 310 CMR 40.0460, and any approval conditions specified by the
Department; and
(b) the certification of the submittal required by 310 CMR 40.0009.
(6) Notwithstanding the provisions of 310 CMR 40.0466(5), an LSP Opinion shall not be
required for Utility-related Abatement Measure Completion Reports documenting response
actions at those Utility-related Abatement Measures described at 310 CMR 40.0462(4).