310 CMR 40.0466

Utility-related Abatement Measure Completion Reports

Year: 2026Length: 354 wordsOfficial source
(1) A Utility-related Abatement Measure Completion Report shall be submitted to the Department within 60 days of the completion of all response actions associated with a Utility- related Abatement Measure. (2) A Utility-related Abatement Measure Completion Report shall contain, at a minimum, the following: (a) a succinct summary of information and data pertaining to the discovery, location and evaluation of encountered contamination, and of all response actions undertaken and/or completed; (b) documentation on the management of Remediation Waste, Remedial Additives and/or Remedial Wastewater managed at the site; and (c) details on any proposed or ongoing active or passive remedial systems that will remain in place at the site. (3) Except as provided in 310 CMR 40.0466(4), a Utility-related Abatement Measure shall not be considered complete until all stockpiled/stored Remediation Waste generated as a result of the Utility-related Abatement Measure is removed from the site pursuant to the provisions of 310 CMR 40.0030. (4) Remediation Waste may be stored, treated, managed, disposed, recycled or reused at a site following the submission to the Department of a Utility-related Abatement Measure Completion Report and Completion Statement only if: (a) such actions are conducted in conformance with the provisions of 310 CMR 40.0030; and (b) a Release Abatement Measure Plan pursuant to the provisions of 310 CMR 40.0440 or a Remedy Implementation Plan pursuant to the provisions of 310 CMR 40.0870 is submitted to the Department as an attachment to the Utility-related Abatement Measure Completion Statement. (5) Except as provided in 310 CMR 40.0466(6), Utility-related Abatement Measure Completion Reports shall be submitted to the Department appended to a Completion Statement form established by the Department for such purposes. The Completion Statement form shall contain: 40.0466: continued (a) an LSP Opinion on whether the Utility-related Abatement Measure was conducted in accordance with 310 CMR 40.0460, and any approval conditions specified by the Department; and (b) the certification of the submittal required by 310 CMR 40.0009. (6) Notwithstanding the provisions of 310 CMR 40.0466(5), an LSP Opinion shall not be required for Utility-related Abatement Measure Completion Reports documenting response actions at those Utility-related Abatement Measures described at 310 CMR 40.0462(4).
310 CMR 40.0466: Utility-related Abatement Measure Completion Reports | Justis AI