310 CMR 45.08
Eligible Project Costs
(1) Costs which the Department determines are necessary for the completion of the project are
eligible for financing in the loan and to receive a subsidy under the loan.
(2) Costs which the Department determines are not necessary for completion of the project are
ineligible for financing in the loan.
(3) Project costs incurred by an eligible borrower prior to the date of issuance of the
Department's project approval certificate are not eligible for a subsidy under the loan, except as
follows:
(a) project design, including preliminary engineering and a project evaluation report, project
construction or related professional services may be approved by the Department prior to the
issuance of a project approval certificate as project costs eligible for subsidy if:
1. The eligible borrower has submitted a written and adequately substantiated request
for approval;
2. The Department's written approval is obtained before initiation of the project and
award of any loan for the project; and
3. The project is included and maintains its status on the current calendar year Intended
Use Plan Project Listing.
(b) The Department's prior approval of costs in accordance with 310 CMR 45.08(3)(a) does
not constitute a commitment to approve financial assistance for any project. Instead, such
costs will be considered eligible project costs only if a loan is made by the Trust for the
project. Accordingly, an eligible borrower receiving the Department's prior approval of costs
in accordance with 310 CMR 45.08(3)(a) proceeds at its own risk.
(4) Costs incurred in excess of the approved project costs are not eligible for financing by the
loan unless the project approval certificate and the loan are both amended to include the cost
increase.
(5) As a loan recipient, an eligible borrower shall exercise its best efforts to accomplish the
work program set forth in the loan within the loan amount. Whenever a loan recipient
reasonably believes that its project costs will exceed or be substantially less than the approved
loan amount, it must promptly notify the Department in writing. The loan recipient must submit
revised cost estimates for the project to the Department as soon thereafter as practicable. Neither
the Department nor the Trust is under any obligation to approve costs in excess of the amount
previously approved in the project approval certificate and loan.
(6) The final eligible project costs shall be the eligible costs approved by the Department upon
completion of the project, unless audited. If such project costs are audited, the final eligible costs
shall be the eligible costs approved by the Department at the completion of the audit.