310 CMR 9.40
Standards for Dredging and Dredged Material Disposal
Any project that includes dredging or dredged material disposal shall comply with the
following requirements:
(1) Limitations on Dredging and Disposal Activity
(a) The project shall not include any dredging of channels, mooring basins, or turnaround
basins to a mean low water depth greater than 20 feet, unless said project:
1. is located within a Designated Port Area; or
2. serves a commercial navigation purpose of state, regional, or federal significance, and
cannot reasonably be located in a Designated Port Area.
(b) If the project is located in an ACEC, the project shall not include any of the following
activities:
1. improvement dredging, unless the dredging is: for the sole purpose of fisheries or
wildlife enhancement; part of an Ecological Restoration Project; or conducted by a public
entity for the sole purpose of the maintenance or restoration of historic, safe navigation
channels or turnaround basins of a minimum length, width and depth consistent with a
Resource Management Plan adopted by the municipality(ies) and approved by the
Secretary.
2. dredged material disposal, except for the sole purpose of beach nourishment, dune
construction, reconstruction or stabilization with proper vegetative cover, the
enhancement of fishery or wildlife resources, or unless the dredged material disposal is
part of an Ecological Restoration Project in accordance with 314 CMR 9.07(1)(c) and
310 CMR 10.11(6)(b) and 310 CMR 40.000: Massachusetts Contingency Plan, if
applicable, provided that any fill or dredged material used in an Ecological Restoration
Project may not contain a chemical above the RCS-1 concentration, as defined in
310 CMR 40.000: Massachusetts Contingency Plan.
(2) Resource Protection Requirements.
(a) The design and timing of dredging and dredged material disposal activity shall be such
as to avoid interference with anadromous/catadromous fish runs. At a minimum, no such
activity shall occur in such areas between March 15th and June 15th of any year, except upon
a determination by the Division of Marine Fisheries, pursuant to M.G.L. c. 130, § 19, that
such an activity will not obstruct or hinder the passage of fish.
(b) The design and timing of dredging and dredged material disposal activity shall be such
as to minimize adverse impacts on shellfish beds, fishery resource areas, and submerged
aquatic vegetation. The Department may consult with the Department of Fish and Game or
the natural resource officer of the municipality regarding the assessment of such impacts.
(3) Operational Requirements for Dredging.
(a) The extent of dredging shall not exceed that reasonably necessary to accommodate the
navigational requirements of the project and provide adequate water circulation.
(b) The shoreward extent of dredging shall be a sufficient distance from the edge of adjacent
marshes to avoid slumping. In general, for improvement dredging projects the edge of the
dredging footprint, including any side cuts, should be at least 25 feet from any marsh
boundary. In areas where significant wake or wash will be generated by vessel traffic,
increased setbacks may be incorporated based on appropriate design calculations.
(c) In general, no basin, canal, or channel shall be dredged deeper than the main channel to
which it is connected.
(d) To the maximum reasonable extent, basins shall have wide openings and short entrance
channels to promote tidal exchange within the basin.
(e) In general, hydraulic dredging shall be favored over mechanical methods, except when
open water disposal of fine grained material is proposed.
(4) Operational Requirements for Dredged Material Disposal.
(a) Where determined to be reasonable by the Department, clean dredged material shall be
disposed of in a manner that serves the purpose of beach nourishment, in accordance with
the following provisions:
1. in the case of a publicly-funded dredging project, such material shall be placed on
publicly-owned eroding beaches; if no appropriate site can be located, private eroding
beaches may be nourished if easements for public access below the existing high water
mark can be secured by the applicant from the owner of the beach to be nourished; or
2. in the case of a privately-funded dredging project, such material may be placed on
any eroding beach.
(b) In the event ocean disposal of dredged material is determined to be appropriate by the
Department, the licensee or permittee shall:
1. publish in the Notice to Mariners the date, time, and proposed route of all ocean
disposal activities and the coordinates of the ocean disposal site, as deemed appropriate
by the U.S. Coast Guard;
2. ensure that transport vessels are not loaded beyond capacity; are equipped with
sudden, high volume release mechanisms; and are at a complete stop when the material
is released; and
3. ensure that disposal occurs within the boundaries of an approved or otherwise
formally designated ocean disposal site; and that the discharge location is marked during
disposal operations by a buoy equipped with a flashing light and radar reflectors which
allow it to be located under variable sea/weather conditions.
(5) Supervision of Dredging and Disposal Activity.
(a) The licensee or permittee shall inform the Department in writing at least three days
before commencing any authorized dredging or dredged material disposal.
(b) The licensee or permittee shall provide, at his or her expense, a dredging inspector
approved by the Department who shall accompany the dredged material while in transit and
during discharges, either upon the scows containing the dredged material or upon the boat
towing them, for the following activities:
1. any offshore disposal;
2. any onshore disposal of dredged material greater than 10,000 cubic yards; or
3. the disposal of materials defined by the Department as potentially degrading or
hazardous.
(c) The name, address, and qualifications of the dredging inspector shall be submitted to the
Department as part of the license or permit application for approval.
(d) Within 30 days after the completion of the dredging, a report shall be submitted to the
Department certified by the dredging inspector, including daily logs of the dredging operation
indicating volume of dredged material, point of origin, point of destination, and other
appropriate information.