310 CMR 9.56
Standards for Facilities of Limited Accommodation
Facilities of Limited Accommodation may be authorized on filled Commonwealth Tidelands
or filled Private Tidelands under certain circumstances where a project site cannot support
Facilities of Public Accommodation for a period of time. Projects including Facilities of Limited
Accommodation as a substitution for Facilities of Public Accommodation described in 310 CMR
9.53(2)(c) and referenced in 310 CMR 9.51(3)(b) must meet any otherwise applicable
requirements of 310 CMR 9.00. The substitution of Facilities of Limited Accommodation for
Facilities of Public Accommodation fulfills the requirements for licensing under 310 CMR
9.31(2)(b)1., provided otherwise applicable requirements are met. The calculation of the
required amount of Facilities of Public Accommodation or the amount of the payment to allow
the substitution shall be based on Facilities of Limited Accommodation located on the ground
floor of buildings on filled Commonwealth Tidelands or Private Tidelands within 100 feet of the
project shoreline. The substitution of Facilities of Limited Accommodation for Facilities of
Public Accommodation may not be inconsistent with an Approved Municipal Harbor Plan under
310 CMR 9.34(2).
(1) An application for a building less than or equal to 75' in height, may substitute Facilities of
Limited Accommodation in up to 50% of the interior space required to be devoted to Facilities
of Public Accommodation. The remainder of the required ground floor interior space, with the
exception of Upper Floor Accessory Services, shall be devoted to Facilities of Public
Accommodation. The requirement that no less than 25% of the otherwise required ground floor
interior space be devoted to Facilities of Public Accommodation may not be waived by the
Department, regardless of foot traffic, density, level of economic development, or the absence
of potential revenues generated by the Facility of Public Accommodation. The Applicant shall
provide notice of the project to the Local Economic Development Authority and any response
it has received from the authority. If the Local Economic Development Authority responds in
writing that the project area has a sufficient level of development to support a Facility of Public
Accommodation, the Department shall not authorize the substitution of a Facility of Limited
Accommodation. If the authority concurs in writing that the project area lacks sufficient
development to support a Facility of Public Accommodation or does not respond to the notice
and the Department does not request additional information within 60 days of receipt of a license
application, the Local Economic Development Authority will be deemed to concur with the
request and the substitution of a Facility of Limited Accommodation shall be authorized. The
first floor design shall be capable of accommodating a Facility of Public Accommodation. 20%
of the net operating income per year generated from the Facilities of Limited Accommodation
shall be paid annually by the project to fund specific construction or activities, approved by the
Department, to activate the waterfront in geographic proximity to the project site. The activation
provided by the specific construction or activities shall extend to evening and/or weekend hours
wherever feasible to compensate for any lack of activation that may result in the substitution of
Facilities of Limited Accommodation for Facilities of Public Accommodation. The funding of
specific construction or activities shall be in addition to applicable requirements at 310 CMR
9.52(1) and 9.53(2). The specific construction or activities to be funded shall be identified by
the Applicant and approved by the Department prior to licensing.
A condition of the license shall include, on or before the 15th anniversary of the first
certificate of occupancy, a requirement for the Department to review the uses of the Facilities
of Limited Accommodation to determine whether the project site could support Facilities of
Public Accommodation, typically based upon foot traffic and density, based on information
provided by the Licensee. The Licensee shall file any relevant information at least six months
prior to the 15th anniversary. If the Department determines that Facilities of Public
Accommodation can be supported and the project is unable to obtain a contrary opinion as
referenced in 310 CMR 9.56(2)(d), the Department shall provide the Licensee with a schedule
for submittals for transition to such uses. If the Department determines that Facilities of Public
Accommodation cannot be supported or the Licensee obtains such an opinion as referenced in
310 CMR 9.56(2)(d), the Department shall specify a time period for a subsequent review. The
Licensee shall certify annually to the Department the amount of space devoted to Facilities of
Limited Accommodation, the use of the space, the net operating income from the Facilities of
Limited Accommodation, and a demonstration of payment for the substitution of Facilities of
Limited Accommodation for Facilities of Public Accommodation as specified in 310 CMR
9.56(2)(f). The Licensee shall provide an electronic copy of the certifications and notice of any
information submitted six months prior to the 15th anniversary review, upon request to any
person who filed comments during the public comment period on the written determination for
the project.
(2) An application for a building greater than 75' in height that can demonstrate that its project
site is unable to fully support Facilities of Public Accommodation, based on foot traffic and
density, may apply for a short-term condition in a license to authorize up to 50% of the interior
space required to be devoted to Facilities of Limited Accommodation in accordance with
310 CMR 10.51 and 10.53 for some portion of the ground floor interior space otherwise required
to be devoted to Facilities of Public Accommodation, provided that no less than 25% of such
required interior space shall be devoted to Facilities of Public Accommodation. The requirement
that no less than 25% of the ground floor interior space otherwise required be devoted to
Facilities of Public Accommodation may not be waived by the Department, regardless of foot
traffic, density, level of economic development, or the absence of potential revenues generated
by the Facility of Public Accommodation. The short-term condition in the license may not
exceed ten years. At the expiration of the term, the ground floor shall be devoted to Facilities
of Public Accommodation, unless the licensee applies for an extension for no more than ten
years and proves that the provisions of 310 CMR 9.56(2)(a) through (d) are met. Applications
for extensions prior to expiration of the term may be allowed only where necessary to maintain
occupancy. For an Applicant seeking a short-term condition in the license to authorize Facilities
of Limited Accommodation in the interior space otherwise required to be devoted to Facilities
of Public Accommodation, 20% of net operating income per year generated from the Facilities
of Limited Accommodation shall be paid by the licensee annually to fund specific construction
or activities, approved by the Department, to activate the waterfront. The activation provided
by the specific construction or activities shall extend to evening and/or weekend hours wherever
feasible to compensate for any lack of activation that may result in the substitution of Facilities
of Limited Accommodation for Facilities of Public Accommodation. The specific construction
or activities to be funded shall be identified by the Applicant and approved by the Department
prior to licensing. The funding of specific construction or activities shall be in addition to
applicable requirements at 310 CMR 9.52(1) and 9.53(2). A project seeking a short term
condition in a license shall:
(a) not be inconsistent with any substitutions, offsets or conditions of approval established
in an Approved Municipal Harbor Plan as provided in 310 CMR 9.34(2);
(b) demonstrate that marketing efforts for at least one year have failed to identify any
prospective Facility of Public Accommodation, even with the offer of up to 50% below
market rents to civic or cultural not-for-profit organizations and a diligent good faith attempt
to locate tenants which shall include advertisements in at least two commercial real estate
marketing publications and listing with a commercial real estate brokerage;
(c) comply with the conditions in the license requiring Facilities of Public Accommodation
unless or until another use is authorized; this requirement may not be waived by the
Department, regardless of foot traffic, density, level of economic development, or the
absence of potential revenues generated by the Facility of Public Accommodation;
(d) obtain the written concurrence of the Local Economic Development Authority that the
project area lacks the level of development to support a Facility of Public Accommodation
at the time of licensing or amendment. If the Local Economic Development Authority does
not respond to the notice and the Department does not request additional information within
60 days of receipt of a license application, the Local Economic Development Authority will
be deemed to concur with the request;
(e) ensure that the first floor design will be capable of accommodating a Facility of Public
Accommodation at the end of the term; and
(f) certify annually the space devoted to Facilities of Limited Accommodation, the use of
the space, the net operating income from those facilities, and demonstration of payment.
(3) A licensee may request an amendment of an existing license to authorize Facilities of
Limited Accommodation, provided the request meets the requirements for an amendment at
310 CMR 9.24, the requirements identified in 310 CMR 9.56(2)(a) through (d), and other
applicable requirements of 310 CMR 9.56(1) or (2). A short-term license condition for Facilities
of Limited Accommodation amending an existing license may be for a limited term of ten years
or 15 years, depending on the height of the building.