314 CMR 21.03
Application for a Watershed Permit
(1) Any Local Government Unit seeking a Watershed Permit may file an application with the
Department. A Watershed Permit application or a Notice of Intent for a Watershed Permit must
be filed pursuant to 310 CMR 15.215(2) to suspend any Title 5 New Construction requirements
under 310 CMR 15.215(2)(b) or to prevent any applicable Title 5 system upgrade requirements
under 310 CMR 15.215(2)(a) from going into effect. Multiple Local Government Units that
share a watershed or sub-watershed may apply jointly for a Watershed Permit, provided they
have entered into a mutually enforceable agreement among the parties that confirms each
applicant's percentage share of the Necessary Nitrogen Load Reductions and provides a
framework to coordinate resource management decision-making and arrangements relating to
the receipt and expenditure of funds for implementation. Unless otherwise stated in the mutually
enforceable agreement among the parties, each Local Government Unit is only responsible for
the proportion of the Controllable Attenuated Nitrogen Load that originates from within its
political boundaries. Authority to enforce the Watershed Permit is reserved to the Department.
(2) Contents of an Application. An application for a Watershed Permit shall contain sufficient
information for the Department to evaluate whether the application meets the applicable review
criteria. Unless otherwise determined by the Department, the application shall include:
(a) a complete application using a form provided by the Department for such purposes;
(b) a Watershed Management Plan, signed and stamped by a Massachusetts Registered
Professional Engineer, for the watershed or sub-watershed that is the subject of the
application and includes:
1. maps depicting the watershed boundary, including each parcel of land within the area
proposed for coverage, and a narrative describing the area proposed to be covered under
a Watershed Permit;
2. a description of the current and historic water quality conditions, including short-term
(daily/seasonal) and long-term (annual) variability;
3. any earlier planning approaches taken prior to filing the application, including any
related findings and recommendations;
4. the types, locations, and timing of any ongoing and proposed TMDL, Alternative
Restoration Plan, MEP Report, or Scientific Evaluation implementation activities within
the watershed or sub-watershed proposed for coverage, including a table identifying:
a. the Updated Nitrogen Load that the area proposed for coverage under the
Watershed Permit contributed to the Surface Waters of the watershed, specifying and
accounting for implementation of all nitrogen reduction measures;
b. projected loads for the following 20 years (projections must include scenarios for
proposed nitrogen-load reducing activities; a MEP Report or other Scientific
Evaluation buildout scenario may suffice);
c. the percentage of Necessary Nitrogen Load Reductions to be attained during the
term of the permit and a concise description of the means of achieving those
specified reductions;
d. the Conventional Control Technologies and Alternative Control Approaches or
Technologies selected for pollutant load reductions and identification of each
permittee that will be responsible for implementing each activity;
e. the area each selected Conventional Control Technology and Alternative Control
Approach or Technology would service;
f. the apportionment of Necessary Nitrogen Load Reductions for each of the
selected Conventional Control Technologies and Alternative Control Approaches or
Technologies;
g. the implementation schedule for each Alternative Control Approach or
Technology proposed, including a timeframe for demonstration, testing, and
acceptance or abandonment of such approaches or technologies;
5. maps depicting the watershed boundary, including each parcel of land within the area
proposed for coverage, and a narrative describing the Core Sewer Area, if applicable, and
the service areas prioritized for wastewater collection and treatment after accounting for
implementation of the selected Alternative Control Approaches and Technologies;
6. documentation of what each permittee proposes to do to reduce its pollutant load in
the watershed or sub-watershed and when those reductions would occur;
7. if Alternative Control Approaches and Technologies are proposed, a contingency plan
for a back-up Conventional Control Technology in the event that the Alternative Control
Approaches and Technologies selected do not function as predicted;
8. a description of each of the proposed pollutant reduction actions to reduce current and
projected loads identified above;
9. cost estimates for the infrastructure and programs associated with the proposed
actions, if available;
10. an implementation schedule, not to exceed 20 years, currently envisioned by the
applicant(s), including a designated set of activities that will occur in each five-year
period and a methodology for analyzing the results of those activities and making
necessary adjustments for each subsequent five-year period of the permit to meet required
load reductions;
11. a watershed or sub-watershed scale monitoring plan that defines the goals of the
monitoring plan, the selected water quality parameters, the method(s) of monitoring to
be employed, the sampling frequency, locations, timing and duration, and a Quality
Assurance Program Plan;
12. the information sources relied upon to develop the proposed Watershed Management
Plan;
13. if the application seeks a Watershed Permit based on a Watershed Management Plan
that will not attain Necessary Nitrogen Load Reductions during the permit term,
documentation showing the financial costs and environmental impact of:
a. complete compliance with those goals and
b. a proposed alternative that makes reasonable progress toward achievement of the
goals in accordance with 314 CMR 21.04(1)(a); and
(c) if there is more than one applicant, an inter-municipal agreement or other legally binding
and appropriate agreement among the applicants that confirms each permittee's percentage
share of the aggregate pollutant reduction responsibility and provides a framework to
administer implementation of the Watershed Management Plan, including arrangements for
the receipt and expenditure of funds.