314 CMR 21.07

Continuation of an Expiring Watershed Permit

Year: 2026Length: 106 wordsOfficial source
(1) In accordance with M.G.L. c. 30A, § 13, a Watershed Permit shall not expire until the Department has issued a decision denying or approving the permittee's renewal application if: (a) the permittee submitted a complete renewal application at least six months prior to the date of expiration of the Watershed Permit; and (b) the Department, through no fault of the permittee, does not issue or deny a renewed permit on or before the expiration date of the previous permit. (2) Effect. Watershed Permits continued under this section remain fully effective and enforceable until the Department issues a decision denying or approving the permittee's renewal application.