345 CMR 3.22
Request for Proposals
(1) Within 60 days of a vote, pursuant to M.G.L. c. 111H, § 17, to initiate site selection, and after
consultation with the Commissioner of the Division of Capital Planning and Operations, the Board shall
issue a Request for Proposals satisfying the requirements of 345 CMR 3.00 and conforming to
345 CMR 3.22.
(2) Each Request for Proposals issued pursuant to 345 CMR 3.22 shall contain the most recent
management plan adopted by the Board and shall require each applicant to submit:
(a) detailed organizational information for the applicant and its proposed subcontractors, including
their legal structure and ownership and control and, in particular, the location of the safety
personnel within the organization; and
(b) the applicant's operational experience, including the background and qualifications of all
officers, directors, partners and principal owners of the Applicant and its subcontractors, and of
the key personnel to be utilized in the performance of any contract with the Board; and
(c) a description of the locations and operating experiences of existing or former operations of the
applicant and its subcontractors; and
(d) theapplicant's andits affiliated entities', principals', subcontractors' and key personnel's history
of compliance with, and any violations of federal, state or local requirements by such persons in any
jurisdiction in which they or any of them has done business, and any criminal indictments or
convictions of such persons or civil litigation brought or judgment entered during the prior five years
against or involving the business activities of such person; and
(e) a financial disclosure statement describing the applicant's financial resources and proposed
revenue plans and demonstrating that the Applicant either possesses the necessary funds or has
reasonable assurance of obtaining the necessary funds to cover the estimated costs of development
and operation of a facility and will have sufficient funds available to carry out facility closure and
post-closure observation and maintenance; and
(f) any and all information relevant to the Board's application of the financial, technical and
management criteria set forth in 345 CMR 3.11 through 3.13, including but not limited to:
1. any Form 10Ks and Form 10Qs that the applicant has filed with the U.S. Securities and
Exchange Commission, during the last five years; and
2. if the applicant did not file Form 10Ks and Form 10Qs with the U.S. Securities and
Exchange Commission during one or more of the past five years, audited financial statements
prepared by a nationally recognized auditing firm for the past five fiscal years and quarterly
financial reports for the past five years; and
3. any material pending legal proceedings, other than routine litigation incidental to the
ordinary course of business, to which the applicant or any of its affiliated entities, principals, or
key personnel is a party or which any of their property is the subject. The applicant shall
include the name of the court or agency in which the proceedings are pending, the date
instituted, the principal parties thereto, a description of the factualbasis alleged to underlie the
proceeding and the relief sought. The applicant shall also include similar information as to any
such proceedings known to be contemplated by government authorities; and
(g) a preliminary facility development, operation, closure, post-closure observation and
maintenance and institutional control plan including a description of the proposed technology or
technologies to be utilized, and of the applicant's staffing plans and personnel training program,
safety and recordkeeping procedures, and contingency plans for facility operations; and
(h) proposed site community, neighboring community and affected community compensation
benefits and guarantees; and
(i) terms under which the applicant will participate in an advisory board that will assist in the
planning and implementation of detailed site characterization.
(3) Each Request for Proposals issued pursuant to 345 CMR 3.22 shall include a statement of
procedures to be followed in responding to the request for proposals, specifying that:
(a) applicants shall be required to respond to the request for proposals within 120 days of the
issuance date specified in the Board vote to issue the Request for Proposal; and
(b) applicants shall be required to pay the Board a fee, determined by the Board, of not less than
$10,000 at the time it submits its response to the Request for Proposals; and
(c) applicants shall be required to agree that there shall be no substitution for the key personnel
to be utilized in the performance of any contact with the Board, identified in the proposal, except
with persons of equal or greater background, experience and educational qualifications and that
such substitutions shall require the prior approval of the Board; and
(d) applicants shall be required to submit, promptly upon their completion, updated Form 10Ks
and Form 10Qs as filed with the U.S. Securities and Exchange Commission, or updated annual
auditedfinancialstatements preparedby a nationally recognized auditing firm and updatedquarterly
financial reports, for each period prior to the selection of the facility operator permit pursuant to
M.G.L. c. 111H, § 27; and
(e) applicants shall be required to submit the following certification:
"I certify under the pains and penalties of perjury that I have personally examined and am
familiar with the information submitted in this form and with those of the attached documents
prepared by or under the direction of the applicant, and that the information contained in this
form and in those of the attached documents prepared by or under the direction of the
applicant is true, accurate and complete."
which shall be signed:
1. ifthe applicant is a corporation, by a principal executive officer of at least the level of vice
president; or
2. if the applicant is a partnership, by a general partner; or
3. if the applicant is a sole proprietor, by the proprietor.
(4) The Board may request of the applicant any additional information it deems necessary to
determine whether the applicant satisfies the financial, technicaland managementcriteriasetforth in 345
CMR 3.11 through 3.14. The applicant shall promptly report any significant change in circumstances