400 CMR 3.05
Permit Application Materials
(1) A project proponent shall include all of the following materials with a permit application
before an issuing authority may deem the application complete:
(a)
A locus map and a resource area map at the appropriate scale as verified by the
applicable authority or an alternative site specific determination by that authority that
establishes the following:
1. The project parcel is located entirely within a "Priority Development Site" as defined
by M.G.L. c. 43D;
2. The project parcel is located entirely within a "Growth District" as defined by the
Executive Office of Housing and Economic Development; and
3. The project parcel is not in a wetland as defined by M.G.L. c. 131, ยง 40, tideland as
defined by M.G.L. c. 91, ยง 1, priority habitat as delineated by the Division of Fisheries
and Wildlife under M.G.L. c. 131A, or an area of critical environmental concern as
designated by the Secretary of Energy and Environmental Affairs.
(b) A certificate issued bythe Secretary of Energy and Environmental Affairs indicating that
the MEPA review process, as required under M.G.L. c. 30, ยงยง 61 through 62I and 301 CMR
11.00: MEPA Regulations is complete for the project.
(c) Written notice shall be provided to each issuing authority that the permit application is
being submitted under the Program. (Note: Project proponents are strongly encouraged to
notify all issuing authorities at the beginning of the MEPA review process that the permit
applications associated with the project will be submitted under the Program. If a project
includes the disposition of state real property, the applicant is also strongly encouraged to
notify the Division of Capital Asset Management of the project's eligibility for the Program
at the beginning of the MEPA review process.)
(d) The name, mailing addresses, e-mail address, and telephone number of the person who
will serve as the applicant's official point of contact for the Program.
(e) Any other materials that the issuing authority requires to be included with a permit
application.
(2) Issuing authorities are encouraged to work together, wherever possible, and may provide
for pre-application conferences to notify the proponent about all permits required for the project
and the materials to be submitted with each permit application. The Interagency Permitting
Board or the Permit Ombudsman may also establish procedures to provide for such conferences.