400 CMR 3.10
Appeals
The commencement of the time period for an administrative or judicial appeal of an
automatic grant of a permit pursuant to 400 CMR 3.07 shall be the date the applicant files notice
of the automatic grant with the issuing authority and Permit Ombudsman.
The 180 or 210 calendar day timeline shall not apply to an administrative appeal following
the issuance of a permit. The procedure for appealing an issuing authority's approval or denial
of a permit shall be controlled by the rules and regulations of that issuing authority.