454 CMR 22.10
Notification Requirements for Deleading Projects
(1) General Requirements. All persons who carry out Deleading Projects, except Owners of
residential premises and Owners' Agents who perform Deleading Work in accordance with
regulations promulgated by the Director of the Childhood Lead Poisoning Prevention Program
at 105 CMR 450.000: Lead Poisoning Prevention and Control and M.G.L. c. 111, § 197(d),
shall satisfy the notification requirements of 454 CMR 22.10 prior to carrying out said work.
All Deleading Work notifications required by 454 CMR 22.10(2) and (3) shall be in a manner
approved jointly by DLS and CLPPP. All applicable sections of each notification form shall be
accurately completed. All Deleading notifications shall minimally include: the address of the
residence or facility, the name of the Owner, the name, business address and license number
(where applicable) of the Deleading Contractor or Lead-safe Renovation Contractor conducting
the Deleading Work, the start date and estimated completion date for the work, the work methods
to be used (scraping, covering, replacement, encapsulation, etc.) and whether the work will be
conducted as Class I, Moderate-risk or Low-risk Deleading Work. All notifications required by
454 CMR 22.10 shall be submitted electronically to: the Director, the Director of CLPPP, the
Massachusetts Historical Commission if the residence is listed on the State Register of Historic
Places, and the local board of health or code enforcement agency. In addition, and in the same
manner, such notifications shall be mailed to all residents of any building in which any Common
Areas are to be deleaded, and to the residents of each individual unit to be deleaded.
(2) Requirements for Class I Deleading Projects. The Deleading Contractor shall provide the
notification specified by 454 CMR 22.10(1) at least ten days before the project start date.
(3) Requirements for Moderate-risk Deleading Projects. Where Moderate-risk Deleading Work
is carried out by a licensed Deleading Contractor, or a Lead-safe Renovation Contractor in
accordance with 454 CMR 22.12(2), said Contractor shall provide the notification specified by
454 CMR 22.10(1) at least five business days before the project start date.
(4) Requirements for Low-risk Deleading Projects. Where Low-risk Deleading Work is carried
out by a licensed Deleading Contractor or Lead-safe Renovation Contractor in accordance with
454 CMR 22.12(3), said Contractor shall provide the notification specified by 454 CMR
22.10(1) at least five business days before the project start date.