700 CMR 13.04
Criteria for Review of Applications
(1) Review of Engineering Plans. The District Highway Director shall require that engineering
plans and specifications provide for safe and efficient access, which protects the operational
integrity of the MassDOT roadway or property. Plan review and approval shall be based on the
standards in the most recent Manual on Uniform Traffic Control Devices (MUTCD), including
the most recent Massachusetts Amendments, MassDOT's Project Development and Design
Guide or its successor, MassDOT's Standard Specifications for Highways and Bridges, and any
then current technical policies or engineering directives, or other manuals and design guides
issued by MassDOT. For Drainage Tie-in applications, all plans and documents shall follow
MassDOT's Drainage Tie-in Standard Operating Procedures, as may be amended from time to
time.
(2) Permit Conditions. The District Highway Director shall condition a Permit to facilitate safe
and efficient traffic operations, to mitigate traffic impacts, to address aesthetic considerations,
and to avoid or minimize environmental damage during the construction period and throughout
the term of the Permit. Such conditions may include, but not be limited to:
(a) Necessary limitations on turning movements;
(b) Necessary measures to ensure the safety of pedestrians, motorists, and those engaged
in the Project, work or activity contemplated under the Permit;
(c)
Restrictions on or requirements for the number and configuration of access points to
serve the land parcel;
(d)
Vehicle trip reduction techniques to be implemented for the development;
(e) Necessary and reasonable efforts to maintain existing levels of service;
(f) Design and construction of necessary highway improvements by the Permittee;
(g) Prescribed restoration measures to ensure the roadway, pavement markings, shoulder,
traffic control devices, signs, guardrail, and all impacted highway devices and appurtenances
are returned to a condition better or equal to the condition prior to commencement of the
permitted work.
(h)
Reimbursement by the Permittee of costs of MassDOT inspection of highway
improvement work;
(i) The requirements of the Section 61 Finding of MassDOT, including the implementation
of Transportation Demand Management measures and Transportation Monitoring Program,
where applicable; and
(j) The requirements of the UAP, where applicable.
Design Exceptions. MassDOT recognizes certain design criteria that, if not met, require
formal approval of design exceptions. These criteria are listed in the Massachusetts Department
of Transportation Project Development and Design Guide and in MassDOT Engineering
Directive E-14-006, as may be amended from time to time. Sufficient documentation of design
exceptions is required to demonstrate that sound engineering judgment was used to design the
improvements. Documentation shall be prepared in accordance with the MassDOT Project
Development and Design Guide and the most current guidance available by MassDOT, and shall
be signed by a Professional Engineer registered in the Commonwealth of Massachusetts. All
design exceptions must be approved by the Chief Engineer. In addition, any proposed work that
does not meet the pedestrian and bicycle accommodation requirements of the MassDOT Healthy
Transportation Policy Directive, as detailed in MassDOT Engineering Directive E-14-006, must
be approved by the Secretary of Transportation. If a design exception is sought as part of a
Permit, an additional 20 business days beyond the time allowed in 700 CMR 13.03(5) shall be
provided for review of the submission.
In addition to exceptions from design criteria, any exceptions to full compliance with
521 CMR: Architectural Access Board, must also be identified in the Access Permit. The
Applicant is responsible for obtaining all necessary variances and approval of design plans and
constructed elements from the local access board. MassDOT shall not issue any Permit that is
not in compliance with 521 CMR and the MassDOT Healthy Transportation Policy Directive,
where applicable.
Review of Related Projects. Permit applications shall be reviewed in the context of the
section(s) of state highway that is (are) affected by traffic to be generated by a Project for which
a Permit is sought. Whenever practical, the District Highway Director shall coordinate review
and issuance of Permits for multiple Projects in proximity to each other in order to facilitate safe
and efficient traffic operations and to avoid or minimize adverse environmental impacts. In
cases where a proposed access is to be shared by multiple development sites, the Applicant(s)
shall provide evidence of the rights of access between the parties involved prior to the issuance
of the Access Permit. In these cases, an Access Permit shall be issued for each development site
under separate ownership.
(5) Section 61 Finding. For all Projects that receive EEA certification of a Final EIR, which
was scoped for a MassDOT Access Permit, MassDOT will issue a Section 61 Finding at the
Applicant's request within 25 business days for Category II Projects or 40 business days for
Category III Projects. The Section 61 Finding shall indicate that MassDOT has completed its
review of the Project in the context of MEPA and that the proposed land use is approved by
MassDOT subject to the conditions outlined in the Finding. Phased Section 61 Findings may
be required under an approved phase-waiver certification issued by the Secretary of EEA. The
Finding shall be incorporated by reference into any Permit to be issued by MassDOT for the
Project. The requirement to issue a Section 61 Finding and a Permit does not preclude the
issuance of a Temporary Access Permit under 700 CMR 13.05(2). The Section 61 Finding will
specify the driveway access and off-site mitigation measures necessary for initial occupancy of
the Project. Additional mitigation measures, if any, and the construction timing of these
additional measures may also be specified in the Section 61 Finding. Plan review of the
measures not required for initial occupancy shall not delay the issuance of the Permit for the
Project for this initial occupancy.
Other Design Features and Considerations. In accordance with 700 CMR 13.04(4),
MassDOT may require the Applicant to include design and development features that are in
keeping with GreenDOT goals and Climate Change Mitigation and Resiliency Measures; where
deemed suitable/practicable given the context of the project and surrounding development and
roadway features. Examples include, but are not limited to, a compliment of electric vehicle
charging stations, bike racks, sidewalks and multiuse paths, bus shelter(s), employee transit
service, and design features to reduce impact of climate change.