700 CMR 14.02
Application for Prequalification of Contractors
(1) General. Any Contractor proposing to bid on work under the direction of the Department
or Other Awarding Authority for which prequalification is required, must furnish for approval
by the Prequalification Committee a statement on forms provided by the Department setting forth
its Aggregate Bonding and Single Bonding Capacity, financial information, adequacy of plant
and equipment, organization, experience and any other pertinent facts as required.
Confidentiality. All information furnished in any statement or Application for
Prequalification by a Contractor shall be held in strict confidence by the Department and its
agents, and shall be used only to determine the Contractor's Aggregate Bonding Capacity, Single
Contract Limit(s) and the Class(es) of Work it shall be entitled to undertake in accordance with
700 CMR 14.00. No information contained in any such statement or Application for
Prequalification shall be imparted or disclosed to any other person without the written consent
of the Contractor.
Out-of-State Contractors. All out-of-state Contractors must show proof of current
registration with the Secretary of State by submitting a Certificate of Good Standing (Foreign
Corporate Certificate) to do business in Massachusetts.
(4) Joint Ventures.
(a)
Subject to the following provisions, two or more Contractors (Joint Ventures) may
combine for occasional bidding purposes, by submitting a joint bid:
1. All Joint Ventures must be prequalified.
2. At least one of the Joint Venturers must be Prequalified in the class of work specified
in the contract documents.
3. The Single Contract Limit of each Joint Venturer may be combined to establish the
Single Contract Limit of the Joint Venture. The Single Contract Limits can only be
combined when they are in the same class of work.
4. The Aggregate & Single Bonding Capacity of each Joint Venturer may be combined
to establish the Aggregate & Single Bonding Capacity of the Joint Venture.
5. The Department shall require submission of a copy of the Joint Venture agreement
or other information deemed necessary.
(b)
If continuous joint venture bidding is desired, a combined Application for
Prequalification may be submitted. The Joint Venture shall be considered in effect for one
year or until one of the joint venturers notifies the Department in writing that the joint
venture is concluded.
(5) Submitting an Application for Prequalification. A request for Prequalification will not be
considered until a completed Application has been submitted. Applications for Prequalification
shall be submitted at least 21 calendar days preceding the day set for opening of bids for work
upon which a Contractor intends to bid. Completed applications for prequalification submitted
less than 21 days preceding the date which is set for bids to be opened may not be executed or
acted upon prior to the bid opening date. A Contractor may file a new Application for
Prequalification at any time; however, no such Application for Prequalification need be
considered by the Prequalification Committee if that Contractor's prequalification status has been
modified, suspended or revoked following a determination by the Prequalification Committee
in accordance with 700 CMR 14.05, until either the expiration of the period of the modification,
suspension or revocation so determined by the Prequalification Committee, or the rendering of
a decision favorable to that Contractor by the Prequalification Appeal Board in accordance with
700 CMR 14.07
Class of Work Desired. Each Contractor shall indicate, in the place provided in the
Application for Prequalification, the particular Class or Classes of Work upon which it desires
to be prequalified for bidding purposes; but such indication shall not be binding upon the
Prequalification Committee in classifying a Contractor.
(a) The Prequalification Committee may prequalify Contractors in one or more Classes of
Work.
(b) The Classes of Work established by the Prequalification Committee, and the definitions
of and/or the prequalification requirements of such Classes of Work may be amended by the
Prequalification Committee from time to time.
(c)
The Prequalification Committee may also establish additional Classes of Work for
specialized contracts. Contractors will be notified of such special Classes of Work in the
Notice to Contractors, Advertisement for Bids, or Instructions to Proposers for the particular
project, and may apply for Prequalification in such special Classes of Work in accordance
with 700 CMR 14.02(9).
Equipment. Contractors must show that they have appropriate and sufficient equipment
available to satisfactorily perform the contemplated class or classes of work. In lieu of actual
equipment on hand, the Contractor may show financial resources sufficient to provide the
necessary equipment for the appropriate Class(es) of Work through a lease agreement for a
period of not less than 12 months from the date of application, and must also provide a copy of
any such lease agreement. In addition to a complete description, a statement as to the condition
of each piece, owned or leased, of equipment may be required. The Department shall have the
right to inspect all equipment in order to determine its operating condition.
(8) Sureties. Contractor's Surety must be authorized to do business in the Commonwealth of
Massachusetts and must be determined to be satisfactory by the Department. "Satisfactory", for
the purposes of 700 CMR 14.02(8), shall mean rated B+ or better by A.M. Best Company and
included on the United States Treasury Department's Listing of Approved Sureties (Department
Circular 570), or such other evaluation as may be designated by the Department from time to
time. The Contractor shall present, along with its Application for Prequalification, a letter from
an authorized representative of the Surety setting forth the Contractor's Aggregate Bonding
Capacity and Single Contract Limit and any limitations imposed thereon by the Surety. Signing
authorization such as Power of Attorney or Attorney-in-Fact must accompany such letter.
(9) Action on Requests for Prequalification. Each Contractor's Application for Prequalification
shall be reviewed by the Prequalification Committee. The Prequalification Committee shall
analyze each statement, verify, to the extent necessary, the information set forth therein,
including the Contractor's Aggregate Bonding Capacity, and establish the Single Contract
Limit(s) of the Contractor and the class(es) of work the Contractor shall be entitled to undertake.
Whenever the Prequalification Committee is not satisfied with the sufficiency of the information
contained in any Application for Prequalification it may require the Contractor to submit
additional information and, pending the filing of such additional information, the Committee
may refuse to allow the Contractor to bid on any work. The Committee may require a personal
interview with principals and key employees of a Contractor when considering its qualifications.
After receipt of a Contractor's Application for Prequalification and such other information as has
been requested by the Prequalification Committee, the Prequalification Committee shall render
its determination. This determination shall consist of either a Prequalification Certificate setting
forth the Contractor's Aggregate Bonding Capacity, Single Contract Project Limit(s) and
Class(es) of Work, or a written determination denying all or part of Contractor's Application for
Prequalification. The determination of the Prequalification Committee shall be subject to the
Contractor's right of appeal as set forth in 700 CMR 14.07.
(10) Subcontractors. The Prequalification Committee may apply any of the criteria described
herein to evaluate the qualifications and performance of subcontractors proposing to perform
subcontract work on projects of the Department and Other Awarding Authorities. Such
evaluations may be considered by the Department and Other Awarding Authorities in making
determinations on subcontractor approvals.