105 CMR 120.024
Plan Review
(A) Prior to construction, the floor plans and equipment arrangements of all new installations,
or modifications of existing installations, utilizing ionizing radiation for diagnostics or
therapeutic purposes shall be submitted to the Agency for review and approval. The installation
shall meet the requirements of 105 CMR 120.420: Appendix A and 105 CMR 120.422:
Appendix C unless specifically exempted. Additional shielding and design requirements are
specified elsewhere in 105 CMR 120.000.
(B) The Agency may require the applicant to utilize the services of a qualified expert to
determine the shielding requirements prior to the plan review and approval.
(C) The approval of such plans shall not preclude the requirement of additional modifications
should a subsequent analysis of operating conditions indicate the possibility of an individual
receiving a dose in excess of the limits prescribed in 105 CMR 120.211, 120.217, 120.218 and
120.221.