810 CMR 8.02
Submission of Standard Contractor Evaluation Forms by Awarding Authorities
(1) Each Awarding Authority shall submit to DCAM a properly completed Standard Contractor
Evaluation Form for the Contractor on each Building Project undertaken by such Awarding Authority
within 70 calendar days from Completion of each Building Project or termination of a Contractor on
a Building Project.
(2) Each Awarding Authority must forward an Interim Evaluation of the Contractor’s performance
at the mid-point of a Building Project’s Completion directly to the Contractor.
(3) All evaluation forms must be completed and signed by one of the following:
(a) For Building Projects that require an Owner’s Project Manager, then said Project Manager
shall complete the Standard Contractor Evaluation Form; or
(b) For Building Projects that do not require an Owner’s Project Manager, then an official from
theAwarding Authority, architect/designer representing the Awarding Authority, or anyother party
responsible for the oversight of the project shall complete all Standard Contractor Evaluation
Forms.
(4) An AwardingAuthoritymust certify in all evaluation forms as to the accuracy of its contents and
shall not negotiate the contents of the Standard Contractor Evaluation Form or the Project Rating with
the Contractor or its representative for any reason.