810 CMR 8.05
Correction of Update Statements
(1) Matters of Form. An Awarding Authority shall not reject a Contractor’s bid because there are
mistakes or omissions of form in the Update Statement submitted with the Contractor’s bid pursuant
to M.G.L. c. 149, § 44D, provided the Contractor promptly corrects those mistakes or omissions
upon request of the Awarding Authority.
(2) Correction of Other Defects. An Awarding Authority may, in its discretion, give a Contractor
notice of non-material errors and omissions in the Contractor’s Update Statement and provide an
opportunity to correct its Update Statement. However, the Contractor shall not be allowed to make
corrections to an Update Statement in the event of material errors or omissions filed in the Update
Statement with the Contractor’s bid. The Awarding Authority shall advise DCAM of any material
erroneous statements or omissions in a Contractor’s Update Statement.