810 CMR 8.07
Capacity Limits
(1) An Awarding Authority shall reject a Contractor’s bid that exceeds the Contractor’s Single
Project Limit shown on the Contractor’s Certificate of Eligibility. A Contractor’s Single Project Limit
must be equal to or greater than the Contractor’s base bid plus all alternates irrespective of whether
none, any, or all such alternates are used.
(2) The Contractor’s Aggregate Work Limit may not be exceeded by the sum of the following:
(a) The annualized value of the work to be performed on the Building Project for which the bid
was submitted, which shall be determined by dividing the Contractor’s bid by the number of years
given to complete the Building Project for which the bid was submitted; and
(b) The total annualized value of the Contractor’s incomplete work under its currently held
contracts,which shall be determine by adding together the annualized value of the incomplete work
under each of the Contractor’s currently held contracts.